Introduction
Please send comments about this plan to the mihini-dev@eclipse.org developer mailing list.
This document lays out the feature and API set for the feature releases of Mihini.
Project Plan
- 0.8: You can find more details on the Project Plan discussions for 0.8
Release plan
Mihini has a stable release every 6 month.
Every major release is maintained for 9 months:
- SR1 is "stable"+3 months,
- SR2 is "stable"+6 months,
- SR3 is "stable"+9 months.
Milestones allow to commit on delivering most priority features and bug fixes first, and move towards stabilization when reaching Release Candidates.
Release calendar
0.8 | 0.9 | 1.0 | |
---|---|---|---|
M1 | 12-Apr-13 | 23-Aug-13 | 21-Feb-14 |
M2 | *skipped* | 4-Oct-13 | 4-Apr-14 |
RC1 | 10-May-13 | 15-Nov-13 | 6-May-14 |
final | 24-May-13 | 6-Dec-13 | 6-Jun-14 |
Maintenance releases | |||
SR1 | 30-Aug-13 | TBD | TBD |
SR2 | 29-Nov-13 | TBD | TBD |
SR3 | 28-Feb-14 | TBD | TBD |