Line 16: | Line 16: | ||
**Release target is 6/25 (W) | **Release target is 6/25 (W) | ||
**IP deadline likely on 1/31 for Ganymede | **IP deadline likely on 1/31 for Ganymede | ||
+ | **There ''might'' be a translation service provided by Babel: | ||
+ | ***Projects provide properties files | ||
+ | ***Babel community translates | ||
+ | ***Projects consume and package translation fragments | ||
**DTP 1.5.2: | **DTP 1.5.2: | ||
***+1 on 2/20 | ***+1 on 2/20 |
Revision as of 13:23, 12 November 2007
← Back to DTP PMC and Project Lead Meeting page
Contents
Attendees
Absent
Agenda
- Announcement: DTP 1.6 build instructions posted.
- (John): Update from Planning Council meeting last week
- Monitor cross project bugs in BZ for Ganymede
- Improve ease-of-use/out-of-box experience
- Concentration on package, rather than project, testing
- Distribution of responsibility for packages
- Look at usability guidelines (to be posted) and make best faith effort
- SQL Query Builder for UI review (?)
- +1 day for +1 dependencies starting with M5. M4 keeps the same schedule.
- Release target is 6/25 (W)
- IP deadline likely on 1/31 for Ganymede
- There might be a translation service provided by Babel:
- Projects provide properties files
- Babel community translates
- Projects consume and package translation fragments
- DTP 1.5.2:
- +1 on 2/20
- Release on 2/28
- (John): Update from EclipseWorld
- Open discussion