Difference between revisions of "Mihini/Project Plan"
< Mihini
(→Release calendar) |
(→Release calendar) |
||
Line 36: | Line 36: | ||
| M1 | | M1 | ||
| | | | ||
− | | | + | | 05-Jul-2013 |
| 23-Aug-13 | | 23-Aug-13 | ||
| 21-Feb-14 | | 21-Feb-14 | ||
Line 48: | Line 48: | ||
| RC1 | | RC1 | ||
| | | | ||
− | | | + | | 02-Aug-2013 |
| 15-Nov-13 | | 15-Nov-13 | ||
| 6-May-14 | | 6-May-14 | ||
Line 54: | Line 54: | ||
| final | | final | ||
| 11-Feb-13 | | 11-Feb-13 | ||
− | | | + | | 09-Aug-2013 |
| 6-Dec-13 | | 6-Dec-13 | ||
| 6-Jun-14 | | 6-Jun-14 |
Revision as of 05:04, 6 June 2013
Introduction
Please send comments about this plan to the mihini-dev@eclipse.org developer mailing list.
This document lays out the feature and API set for the feature releases of Mihini.
Project Plan
- 0.9: You can find more details on the Project Plan discussions for 0.8
Release plan
Mihini has a stable release every 6 month.
Every major release is maintained for 9 months:
- SR1 is "stable"+3 months,
- SR2 is "stable"+6 months,
- SR3 is "stable"+9 months.
Milestones allow to commit on delivering most priority features and bug fixes first, and move towards stabilization when reaching Release Candidates.
Release calendar
0.8 | 0.9 | 0.10 | 1.0 | |
---|---|---|---|---|
M1 | 05-Jul-2013 | 23-Aug-13 | 21-Feb-14 | |
M2 | *skipped* | 4-Oct-13 | 4-Apr-14 | |
RC1 | 02-Aug-2013 | 15-Nov-13 | 6-May-14 | |
final | 11-Feb-13 | 09-Aug-2013 | 6-Dec-13 | 6-Jun-14 |
Maintenance releases | ||||
SR1 | 15-Apr-13 | 30-Aug-13 | TBD | TBD |
SR2 | 10-Jun-13 | 29-Nov-13 | TBD | TBD |
SR3 | 28-Feb-14 | TBD | TBD |