Week by Week Plan to get to the March Demo. | Week by Week Plan to get to the March Demo. | ||
− | == Resource Modeling == | + | == Resource Modeling; Steve Jerman == |
{{CTable|tableWidth=100%}} | {{CTable|tableWidth=100%}} | ||
| Date | | Date | ||
Line 26: | Line 26: | ||
| Ali | | Ali | ||
|} | |} | ||
− | == Data Collection == | + | == Data Collection; Don Ebright == |
{{CTable|tableWidth=100%}} | {{CTable|tableWidth=100%}} | ||
| Date | | Date | ||
Line 43: | Line 43: | ||
|- | |- | ||
|} | |} | ||
− | == Data Reporting == | + | == Data Reporting; Craig Thomas == |
This is the sub-project plan with milestones. | This is the sub-project plan with milestones. | ||
Revision as of 16:18, 1 March 2007
Week by Week Plan to get to the March Demo.
Resource Modeling; Steve Jerman
Date | Milestone | Dependencies | Who |
2-Feb-2007 | SMLIF editor
(The code will be fully functional by Feb 2) |
None | Ali |
2-Feb-2007 | Import from SMLIF and export to SMLIF actions
(The code will be fully functional by Feb 2) |
None | David |
2-Feb-2007 | SML and SMLIF documents
(the instances are already available in CVS; Ali to make any required changes) |
None | Ali |
Data Collection; Don Ebright
Date | Milestone | Dependencies | Who |
1-Mar-2007 | Architecture and plan documents for June deliverables
|
None | Don |
Data Reporting; Craig Thomas
This is the sub-project plan with milestones.
Information reviewed with Sheldon and Mark (Cthomas.groundworkopensource.com 14:29, 15 February 2007 (EST))
Date | Milestone | Dependencies | Who |
26-Jan-2007 |
Topologies Report |
|
Sheldon |
2-Feb-2007 |
Nodes Report, Properties Report |
|
Sheldon |
9-Feb-2007 |
"top 10 report" of CBE data (https://bugs.eclipse.org/bugs/show_bug.cgi?id=172538) |
|
Sheldon |
9-Feb-2007 | Update setup instructions with current information Status as of 22-Feb-2007: complete. |
None | Sheldon |
16-Feb-2007 |
Status as of 15-Feb-2007: complete. |
|
Sheldon |
2-Mar-2007 |
Architecture and plan documents for June deliverables
|
none | Craig, Sheldon, Mark |