Difference between revisions of "Agenda for 09/28/06 Aperi Development Status Meeting"
Line 45: | Line 45: | ||
** [http://www.eclipse.org/aperi/events/EclipseSummit-Preparations.html Eclipse Summit Items] | ** [http://www.eclipse.org/aperi/events/EclipseSummit-Preparations.html Eclipse Summit Items] | ||
** Meeting time conflict on 10/12, 11/9, and 12/7. | ** Meeting time conflict on 10/12, 11/9, and 12/7. | ||
+ | ** Meeting room conflict on 10/5 (A141) |
Revision as of 17:08, 20 September 2006
Aperi Wiki Home Aperi Meetings Aperi Development Meetings
Dial in numbers:
Toll Free: 866-617-3597 International: 210-795-0625 Passcode: 6121165
Agenda:
- Project Leader Notes (Ted)
- Release Lead Notes (Dave)
- Status on initial coontribution items:
Task | Duration | Start | Finish |
---|---|---|---|
Eclipse legal Review | 14 days | Thu 9/7/06 | Tue 9/26/06 |
Load code into cvs at Eclipse | 1 day | Wed 9/27/06 | Wed 9/27/06 |
Contribution downloadable in Eclipse cvs | 0 days | Wed 9/27/06 | Wed 9/27/06 |
Build instructions - Eclipse cvs | 5 days | Wed 9/27/06 | Tue 10/3/06 |
- Updated Schedule
- Phase 2:
- Design
- Implementation
- Test
- Smoke Test Issues
- ID
- Derby issues
- Action Items
Item | Owner | Target | Status |
---|---|---|---|
Third Party Dependency Questionnaire | Helen | 09/21/06 | Questionnaires submitted 9/6. Checking with Eclipse on Monday for status. |
- Other:
- Eclipse Summit Items
- Meeting time conflict on 10/12, 11/9, and 12/7.
- Meeting room conflict on 10/5 (A141)