(New page: ← Back to DTP PMC Meeting Page ==Attendees== *Brian Fitzpatrick *Linda Chan *John Graham *Sheila Sholars ==Regrets== ==Agenda== *Open discussion ==Minutes== =...) |
|||
Line 9: | Line 9: | ||
==Agenda== | ==Agenda== | ||
+ | *1.6.1 Rampdown policy | ||
+ | **M2 is August 25, 2008 | ||
+ | **Ganymede SR1 release train as a +1 project. Those dates are [[http://wiki.eclipse.org/Ganymede#Coordinated_Service_Releases_.28Proposed.29[here]]. | ||
+ | ***September 2, 2008 - RC1 | ||
+ | ***September 9, 2008 - RC2 | ||
+ | ***September 16, 2008 - RC3 (Final Release, available September 24, 2008) | ||
+ | *Proposed policy: | ||
+ | **Open for fixes until afternoon of August 25, 2008 (SH time) | ||
+ | **Team lead approval needed for any fixes the week of August 25 - August 28 | ||
+ | **August 29 (SH time) build will be the RC1 integration build. Test on August 29 & September 1, rebuild if issues arise | ||
+ | **Week of September 1 - September 4, PMC approval required (reasons, implications, testing, patch) | ||
+ | **September 5 (SH time) build will be the RC2 integration build. Test on September 5 & September 8, rebuild if issues arise | ||
+ | **Just testing after that until September 16 | ||
+ | |||
*Open discussion | *Open discussion | ||
Revision as of 14:21, 18 August 2008
← Back to DTP PMC Meeting Page
Attendees
- Brian Fitzpatrick
- Linda Chan
- John Graham
- Sheila Sholars
Regrets
Agenda
- 1.6.1 Rampdown policy
- M2 is August 25, 2008
- Ganymede SR1 release train as a +1 project. Those dates are [[here].
- September 2, 2008 - RC1
- September 9, 2008 - RC2
- September 16, 2008 - RC3 (Final Release, available September 24, 2008)
- Proposed policy:
- Open for fixes until afternoon of August 25, 2008 (SH time)
- Team lead approval needed for any fixes the week of August 25 - August 28
- August 29 (SH time) build will be the RC1 integration build. Test on August 29 & September 1, rebuild if issues arise
- Week of September 1 - September 4, PMC approval required (reasons, implications, testing, patch)
- September 5 (SH time) build will be the RC2 integration build. Test on September 5 & September 8, rebuild if issues arise
- Just testing after that until September 16
- Open discussion