== COSMOS 1.0 Milestone Plan ==
+
= COSMOS 1.0 Release Plan - Draft - Updated 4/22/2008 =
[[COSMOS_Release_Plan_Working_Draft|Working Draft]]
+
 
+
=== Community Systems Management Open Source (COSMOS) 1.0 Milestone Plan (Draft) ===
+
  
 +
== Overview ==
 
Please send comments about this plan to the [mailto:cosmos-mgmt@eclipse.org cosmos-mgmt@eclipse.org] project management mailing list.
 
Please send comments about this plan to the [mailto:cosmos-mgmt@eclipse.org cosmos-mgmt@eclipse.org] project management mailing list.
  
Line 15: Line 13:
 
* [[#Features|Features]]
 
* [[#Features|Features]]
  
This plan describes the deliverables, milestones, and plan items for the four projects under COSMOS.  Each plan item covers a feature or API that is to be added to COSMOS, or some aspect of COSMOS that is to be improved.  Each plan item has its own entry in the COSMOS bugzilla database, with a title and a concise summary (usually a single paragraph) that explains the work item at a suitably high level so that everyone can readily understand the work item.  
+
This plan describes the deliverables, milestones, and plan items for the COSMOS project.  Each plan item covers a feature or API that is to be added to COSMOS, or some aspect of COSMOS that is to be improved.  Each plan item has its own entry in the COSMOS bugzilla database, with a title and a concise summary (usually a single paragraph) that explains the work item at a suitably high level so that everyone can readily understand the work item.  
  
  
 
Fixing bugs, improving test coverage, documentation, examples, performance tuning, usability, etc. are considered routine ongoing maintenance activities and are not included in this plan unless they would also involve a significant change to the API or feature set, or involve a significant amount of work. The intent of the plan is to account for all interesting feature work.  
 
Fixing bugs, improving test coverage, documentation, examples, performance tuning, usability, etc. are considered routine ongoing maintenance activities and are not included in this plan unless they would also involve a significant change to the API or feature set, or involve a significant amount of work. The intent of the plan is to account for all interesting feature work.  
  
==== Release Deliverables ====
+
== Release Deliverables ==
  
 
The following release deliverables are provided:  
 
The following release deliverables are provided:  
 
* Runtime  
 
* Runtime  
 +
* Tooling
 
* Source  
 
* Source  
 
* Examples  
 
* Examples  
Line 30: Line 29:
 
* Data Visualization Implementation
 
* Data Visualization Implementation
 
* Resource Modeling Implementation
 
* Resource Modeling Implementation
 +
* Management Enablement Implementation
 +
* CMDBf Implementation
  
==== Release Milestones ====
+
== Release Milestones ==
 
+
This COSMOS 1.0 is targeted for general availability on 27-June-2008.  All deliverables will be available for download as soon as the release has been tested and validated in the target configurations.  There is an allocation of resource to defect removal in all iterations. The first Iterations 1-10 will contain the bulk of the enhancement work, while Iteration 11 will mainly be used to stabilize and shut down the release.
+
  
Each project leader will send a notification to the project leadership team upon completion of iteration testingOnce all projects have indicated that they have finished iteration testing, a candidate build will be flagged and the teams can begin checking in code for the next iteration.
+
This COSMOS 1.0 is targeted for general availability on 14-November-2008.  All deliverables will be available for download as soon as the release has been tested and validated in the target configurationsThere is an allocation of resource to defect removal in all iterations. The first Iterations 1-10 will contain the bulk of the enhancement work, while Iterations 11-13 will mainly be used to stabilize and shut down the release.  
  
  
Line 245: Line 244:
 
|'''Fri 01/25/2008'''
 
|'''Fri 01/25/2008'''
 
|'''Mon 11/26/2007'''
 
|'''Mon 11/26/2007'''
|
+
|'''Fri 01/25/2008'''
 
|
 
|
 
|
 
|
Line 254: Line 253:
 
|Fri 01/11/2008
 
|Fri 01/11/2008
 
|Mon 11/26/2007
 
|Mon 11/26/2007
|
+
|Fri 01/11/2008
 
|Development & Bug Fixes
 
|Development & Bug Fixes
 
|
 
|
Line 271: Line 270:
 
|Mon 01/14/2008
 
|Mon 01/14/2008
 
|Fri 01/25/2008
 
|Fri 01/25/2008
|
+
|Mon 01/14/2008
|
+
|Fri 01/25/2008
 
|Validation Testing & Documentation
 
|Validation Testing & Documentation
 
|
 
|
Line 280: Line 279:
 
|'''Mon 01/28/2008'''
 
|'''Mon 01/28/2008'''
 
|'''Fri 03/07/2008'''
 
|'''Fri 03/07/2008'''
|
+
|'''Mon 01/28/2008'''
|
+
|'''Fri 03/07/2008'''
 
|
 
|
 
|
 
|
Line 289: Line 288:
 
|Mon 01/28/2008
 
|Mon 01/28/2008
 
|Wed 02/20/2008
 
|Wed 02/20/2008
|
+
|Mon 01/28/2008
|
+
|Wed 02/20/2008
 
|Development & Bug Fixes
 
|Development & Bug Fixes
 
|
 
|
Line 307: Line 306:
 
|Mon 02/25/2008
 
|Mon 02/25/2008
 
|Fri 03/07/2008
 
|Fri 03/07/2008
|
+
|Mon 02/25/2008
|
+
|Fri 03/07/2008
 
|Validation Testing & Documentation
 
|Validation Testing & Documentation
 
|
 
|
Line 316: Line 315:
 
|'''Fri 03/07/2008'''
 
|'''Fri 03/07/2008'''
 
|'''Fri 03/07/2008'''
 
|'''Fri 03/07/2008'''
|
+
|'''Fri 03/07/2008'''
|
+
|'''Fri 03/07/2008'''
 
|Available for POCs
 
|Available for POCs
 
|
 
|
Line 325: Line 324:
 
|'''Mon 03/10/2008'''
 
|'''Mon 03/10/2008'''
 
|'''Fri 05/02/2008'''
 
|'''Fri 05/02/2008'''
|
+
|'''Mon 03/10/2008'''
 
|
 
|
 
|
 
|
Line 334: Line 333:
 
|Mon 03/10/2008
 
|Mon 03/10/2008
 
|Wed 04/16/2008
 
|Wed 04/16/2008
|
+
|Mon 03/10/2008
 
|
 
|
 
|Development & Bug Fixes
 
|Development & Bug Fixes
Line 381: Line 380:
 
|
 
|
 
|
 
|
|Final Validation Testing, Documentation & Shutdown
+
|Validation Testing & Documentation
 
|
 
|
 
|-
 
|-
|'''COSMOS 1.0 Availability'''
+
!'''**Milestone 3**'''
 
|'''1 day'''
 
|'''1 day'''
 
|'''Fri 06/27/2008'''
 
|'''Fri 06/27/2008'''
 
|'''Fri 06/27/2008'''
 
|'''Fri 06/27/2008'''
 +
|
 +
|
 +
|Available for PoCs
 +
|
 +
|-
 +
|'''Iteration 12'''
 +
|'''6 weeks'''
 +
|'''Mon 06/30/2008'''
 +
|'''Fri 08/08/2008'''
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
|  i12 Development
 +
|4 weeks
 +
|Mon 06/30/2008
 +
|Wed 07/23/2008
 +
|
 +
|
 +
|Development & Bug Fixes
 +
|
 +
|-
 +
|**High-level designs for i13 Complete**
 +
|1 day
 +
|Fri 07/25/2008
 +
|Fri 07/25/2008
 +
|
 +
|
 +
|High-level designs and sizings
 +
|
 +
|- 
 +
|  i12 Testing
 +
|2 weeks
 +
|Mon 07/28/2008
 +
|Fri 08/08/2008
 +
|
 +
|
 +
|Validation Testing & Documentation
 +
|
 +
|-
 +
|'''COSMOS 0.9 Availability'''
 +
|'''1 day'''
 +
|'''Fri 08/08/2008'''
 +
|'''Fri 08/08/2008'''
 +
|
 +
|
 +
|0.9 Release
 +
|
 +
|-
 +
|'''Iteration 13'''
 +
|'''6 weeks'''
 +
|'''Mon 08/11/2008'''
 +
|'''Fri 09/19/2008'''
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
|  i13 Development
 +
|4 weeks
 +
|Mon 08/11/2008
 +
|Wed 09/03/2008
 +
|
 +
|
 +
|Development & Bug Fixes
 +
|
 +
|- 
 +
|  i13 Testing
 +
|2 weeks
 +
|Mon 09/08/2008
 +
|Fri 09/19/2008
 +
|
 +
|
 +
|Validation Testing & Documentation
 +
|
 +
|-
 +
|'''Iteration 14'''
 +
|'''8 weeks'''
 +
|'''Mon 09/22/2008'''
 +
|'''Fri 11/14/2008'''
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
|  i14 Development
 +
|5 weeks
 +
|Mon 09/22/2008
 +
|Wed 10/22/2008
 +
|
 +
|
 +
|Development & Bug Fixes
 +
|
 +
|- 
 +
|  i14 Testing
 +
|3 weeks
 +
|Mon 10/27/2008
 +
|Fri 11/14/2008
 +
|
 +
|
 +
|Final Validation Testing, Documentation & Shutdown
 +
|
 +
|-
 +
|'''COSMOS 1.0 Availability'''
 +
|'''1 day'''
 +
|'''Fri 11/14/2008'''
 +
|'''Fri 11/14/2008'''
 
|
 
|
 
|
 
|
Line 394: Line 501:
 
|}
 
|}
  
==== Themes ====
+
== Release Themes ==
 +
 
 +
The COSMOS project adopted the following themes which represent the key focus areas for COSMOS enhancements in the year ahead.
  
The COSMOS project adopted the following theme which represents the key focus area for COSMOS enhancements in the year ahead.
 
 
* Provide an open platform that is standards-based for extensibility and openness
 
* Provide an open platform that is standards-based for extensibility and openness
 
* Provide exemplary tools for monitoring and management of popular open distributed platforms
 
* Provide exemplary tools for monitoring and management of popular open distributed platforms
 
* Establish base framework:
 
* Establish base framework:
 
** Data collection normalization and persistence framework
 
** Data collection normalization and persistence framework
** Validation/Editing/Viewing framework based on SML
+
** CMDB Federation (CMDBf) support framework
 +
** Validation/Editing/Viewing framework based on Service Modeling Language (SML)
 +
** Deployment framework for management enablement using Solution Deployment Descriptor (SDD)
  
==== Project Designs ====
+
== Project Designs ==
 +
<font color="red">'''<NEEDS TO BE UPDATED>'''</font>
  
 
The COSMOS project is comprised of four projects, managed in a coordinated fashion, across which the plan items are allocated.  COSMOS projects include:
 
The COSMOS project is comprised of four projects, managed in a coordinated fashion, across which the plan items are allocated.  COSMOS projects include:
Line 414: Line 525:
 
Designs for these projects will be checked in to the COSMOS bugzilla database so that developers can reference them as they create designs for specific plan items.
 
Designs for these projects will be checked in to the COSMOS bugzilla database so that developers can reference them as they create designs for specific plan items.
  
==== Features ====
+
== Features ==
  
Plan items targeted for this release represent the addition of new features or areas where existing features will be significantly reworked or enhanced.  Plan items are allocated to the projects indicated above.  
+
Plan items targeted for this release represent the addition of new features or areas where existing features will be significantly reworked or enhanced.  Plan items are allocated to the projects indicated above.
  
'''COSMOS Data Collection Project Plan Items'''
+
=== Milestone 1 Objectives (i1 - i4) ===
{|border = "1" cellpadding="1"
+
|-
+
!Status
+
!Target iteration
+
!Description
+
|-
+
|In Plan
+
|i2
+
|Define and build the COSMOS data collection framework. This includes: definition and implementation of the component assembly framework SPI, implementation of binding and component context loading services for an Equinox OSGi host, definition of component APIs supporting all currently defined component types (data source, data sink, filter, transformer), base classes for all currently defined component types, component assembly schema, automated build process for the data collection component, user documentation for adopters of the framework, and automated unit test cases.  The following enhancements are being used to track this work: [https://bugs.eclipse.org/bugs/show_bug.cgi?id=174347 (174347)] [https://bugs.eclipse.org/bugs/show_bug.cgi?id=177821 (177821)] [https://bugs.eclipse.org/bugs/show_bug.cgi?id=180318 (180318)] .
+
|-
+
|In Plan
+
|i4
+
|
+
* Intitial DC Domain Support [https://bugs.eclipse.org/bugs/show_bug.cgi?id=187805 (187805)]
+
* Query component for SML documents based on xpath [https://bugs.eclipse.org/bugs/show_bug.cgi?id=188399 (188399)]
+
* Statistical data sink supporting JMX properties [https://bugs.eclipse.org/bugs/show_bug.cgi?id=188765 (188765)]
+
* Statistical query components supporting JMX properties [https://bugs.eclipse.org/bugs/show_bug.cgi?id=188776 (188776)]
+
* Database schema for statistical model [https://bugs.eclipse.org/bugs/show_bug.cgi?id=188769 (188769)]
+
* Provide a COSMOS Managment Domain to help bootstrap the Data Collection framework https://bugs.eclipse.org/bugs/show_bug.cgi?id=188942 (188942)]
+
* Implement the data set provider registry [https://bugs.eclipse.org/bugs/show_bug.cgi?id=188945 (188945)]
+
* Database Schema for Data Provider Registry [https://bugs.eclipse.org/bugs/show_bug.cgi?id=189132 (189132)]
+
|}
+
  
 +
* Provide tools that support systems management data conforming to the Service Modeling Language (SML) and SML-Interchange Format (SML-IF) standards, including SML and SML-IF document validation, SML-IF editing, import of SML-IF documents and export to SML-IF documents
 +
* Create example data center described in SML format
 +
* Provide standard APIs for accessing COSMOS data from heterogeneous clients
 +
* Create data collectors that gather data from Common Base Event (CBE) logs, JMX, and WSDM Event Format (WEF) sources
 +
* Provide preset reports to visualize event and statistical data
 +
* Create a data store to persist statistical information based on the standard SDMX specification
 +
* Create a relational data store for the persistence of event information and statistical information
 +
* Create a web-based viewer composed of Web 2.0 gadgets to thoroughly examine data from SML-IF documents
 +
* Provide extension points to create complementary visualizations in the form of Web 2.0 gadgets and BIRT reports
  
 
'''COSMOS Data Visualization Project Plan Items'''
 
{|border = "1" cellpadding="1"
 
|-
 
!Status
 
!Target iteration
 
!Description
 
|-
 
|In Plan
 
|i4
 
|
 
* Visualize a read-only model (the ui is not expected to modify the resource model or data collection information), provide a simple navigation system based on a resource graph, show properties of a resource, and provide visualization of collected resource information.  [https://bugs.eclipse.org/bugs/show_bug.cgi?id=180069 (180069)] [https://bugs.eclipse.org/bugs/show_bug.cgi?id=180073 (180073)]
 
* Create Data Retrieval Service framework and components. [https://bugs.eclipse.org/bugs/show_bug.cgi?id=184242 (184242)]
 
* Create Graphical Visualization Service framework and components. [https://bugs.eclipse.org/bugs/show_bug.cgi?id=184243 (184243)]
 
* Create Presentation Service framework and components. [https://bugs.eclipse.org/bugs/show_bug.cgi?id=184245 (184245)]
 
|}
 
 
  
'''COSMOS Resource Modeling Project Plan Items'''
+
[[COSMOS_Milestone1_Plan_Items|COSMOS Milestone 1 Plan Items]]
{|border = "1" cellpadding="1"
+
 
|-
+
=== Milestone 2 Objectives (i5 - i9) ===
!Status
+
 
!Target iteration
+
* Provide framework for implementing CMDBf query and registration services
!Description
+
* Create Eclipse-integrated toolkit for creating data managers and management data repositories (MDRs)
|-
+
* Provide ability to register an MDR with the COSMOS framework
|In Plan
+
* Provide ability to register and deregister an MDR with a federating CMDB, using the COSMOS UI
|i2
+
* Provide ability to query an MDR from the COSMOS UI, using query builder driven by CMDBf metadata
|
+
* Create example MDRs, including a simplistic one and one based on the example data center
* Provide validator for SML and SML-IF documents, based on the SML 1.0 specification
+
* Provide ability to visualize a CMDBf query response
* Provide import from SML-IF and export to SML-IF action for a file based SML repository
+
* Provide support for deploying to J2EE environments (for example, Tomcat)
* Provide simple SML-IF editor for creating SML-IF documents from a file based repository
+
* Provide full test suite showing implementation examples
|-
+
 
|In Plan
+
 
|i3
+
[[COSMOS_Use_Cases|COSMOS Milestone 2 Use Cases]]
|SML validator should accept input other than File resources. [https://bugs.eclipse.org/bugs/show_bug.cgi?id=181594 (181594)]
+
 
|-
+
=== Milestone 3 Objectives (i10 - i11) ===
|In Plan
+
 
|i4
+
* Update SML Validator to align with latest SML specification
|
+
* Enhance CMDB Federation Toolkit
* Create preliminary representation of resources. [https://bugs.eclipse.org/bugs/show_bug.cgi?id=178590 (178590)]
+
* Provide support for non-COSMOS MDRs and clients using vanilla web services
* Provide a data layer for Data Visualization access to resource, which includes the following services: data filtering, data grouping, data sorting and data counts. [https://bugs.eclipse.org/bugs/show_bug.cgi?id=180068 (180068)]
+
* Provide overall quality and stabilization improvements and reduce defect backlog
* Provide the concept of a repository under the resource modeling subproject. [https://bugs.eclipse.org/bugs/show_bug.cgi?id=179828 (179828)]
+
* Establish clear set of public APIs & complete externalization of strings
* Create more test cases for the validation plug-in. [https://bugs.eclipse.org/bugs/show_bug.cgi?id=172682 (172682)]
+
 
|}
+
 
 +
[[COSMOS_Use_Cases|COSMOS Milestone 3 Use Cases]]
 +
 
 +
=== Milestone 4/COSMOS 1.0 GA Objectives (i12-i14) ===
 +
 
 +
* Provide SDD Tooling and Runtime for management enablement
 +
* Finalize API
 +
* Enhance quality and documentation
 +
 
 +
 
 +
 
 +
 
 +
=== Proposal for Themes - i11 - i13 ===
 +
<font color="blue">
 +
From Ruth Lee:
 +
 
 +
My proposal for the COSMOS iterations between now and November is (Themes in italics):
 +
 
 +
i11: ''Quality and Extensibility'': identify API, document API, drive more adoption, ideally get more activity on the mailing list and newsgroup.
 +
Purpose: Increase adoption of COSMOS, stabilize COSMOS, and prove COSMOS as an extensible framework.
 +
 
 +
i12: ''Accessibility, internationalization and localization, upgrade path''
 +
Purpose: Provide support for the pervasive themes in Eclipse. (Suspect this is needed to qualify releasing a 1.0.)
 +
 
 +
i13: ''Quality'': Reduce defect backlog, finish any items needed to release a 1.0
 +
Purpose: Wind-down, clean up any remaining items that we think are needed to quality to release 1.0 in November.  
 +
 
 +
'''Delineation between M3 and 1.0:'''
 +
M3 is English-only, non-accessible. 1.0 will be enabled for translation (although nothing will be translated), it will be globalized, accessible, and the upgrade path plan will be in place.
 +
</font>

Revision as of 15:18, 14 May 2008

COSMOS Wiki > COSMOS Work Items

COSMOS 1.0 Release Plan - Draft - Updated 4/22/2008

Overview

Please send comments about this plan to the cosmos-mgmt@eclipse.org project management mailing list.


This document lays out the feature and API set for the COSMOS Tech Preview releases.

This plan describes the deliverables, milestones, and plan items for the COSMOS project. Each plan item covers a feature or API that is to be added to COSMOS, or some aspect of COSMOS that is to be improved. Each plan item has its own entry in the COSMOS bugzilla database, with a title and a concise summary (usually a single paragraph) that explains the work item at a suitably high level so that everyone can readily understand the work item.


Fixing bugs, improving test coverage, documentation, examples, performance tuning, usability, etc. are considered routine ongoing maintenance activities and are not included in this plan unless they would also involve a significant change to the API or feature set, or involve a significant amount of work. The intent of the plan is to account for all interesting feature work.

Release Deliverables

The following release deliverables are provided:

  • Runtime
  • Tooling
  • Source
  • Examples
  • Component Tests
  • Data Collection Implementation
  • Data Visualization Implementation
  • Resource Modeling Implementation
  • Management Enablement Implementation
  • CMDBf Implementation

Release Milestones

This COSMOS 1.0 is targeted for general availability on 14-November-2008. All deliverables will be available for download as soon as the release has been tested and validated in the target configurations. There is an allocation of resource to defect removal in all iterations. The first Iterations 1-10 will contain the bulk of the enhancement work, while Iterations 11-13 will mainly be used to stabilize and shut down the release.


Release Milestones

Milestone Duration Planned Start Date Planned End Date Actual Start Date Actual End Date Description Comments
Iteration 1 8 weeks Tues 01/02/2007 Fri 02/23/2007 Tues 01/02/2007 Fri 02/23/2007 Demo development
Iteration 2 6 weeks Mon 02/26/2007 Fri 04/06/2007 Mon 02/26/2007 Fri 04/06/2007
i2 Development 5 weeks Mon 02/26/2007 Fri 03/30/2007 Mon 02/26/2007 Fri 03/30/2007 Development & Bug Fixes
i2 Testing 1 week Mon 04/02/2007 Fri 04/06/2007 Mon 04/02/2007 Fri 04/06/2007 Validation Testing
Iteration 3 6 weeks Mon 04/09/2007 Fri 05/18/2007 Mon 04/09/2007 Fri 05/18/2007
i3 Development 5 weeks Mon 04/09/2007 Fri 05/11/2007 Mon 04/09/2007 Fri 05/11/2007 Development & Bug Fixes
i3 Testing 1 week Mon 05/14/2007 Fri 05/18/2007 Mon 05/14/2007 Fri 05/18/2007 Validation Testing
Iteration 4 6 weeks Mon 05/21/2007 Fri 06/29/2007 Mon 05/21/2007 Fri 06/29/2007 Shut down and Testing
i4 Development 4 weeks Mon 05/21/2007 Fri 06/15/2007 Mon 05/21/2007 Fri 06/15/2007 Bug Fixes
i4 Testing 2 weeks Mon 06/18/2007 Fri 06/29/2007 Mon 06/18/2007 Fri 06/29/2007 Validation Testing
**Milestone 1** 1 day Fri 06/29/2007 Fri 06/29/2007 Fri 06/29/2007 Fri 06/29/2007 Available for POCs
Iteration 5 6 weeks Mon 07/02/2007 Fri 08/10/2007 Mon 07/02/2007 Fri 08/17/2007
i5 Development 5 weeks Mon 07/02/2007 Fri 08/03/2007 Mon 07/02/2007 Fri 08/10/2007 Development & Bug Fixes
i5 Testing 1 week Mon 08/06/2007 Fri 08/10/2007 Mon 08/13/2007 Fri 08/17/2007 Validation Testing & Documentation
Iteration 6 6 weeks Mon 08/13/2007 Fri 09/28/2007 Mon 08/20/2007 Fri 10/02/2007 Extended test pass by 1 week
i6 Development 5 weeks Mon 08/13/2007 Fri 09/14/2007 Mon 08/20/2007 Fri 09/14/2007 Development & Bug Fixes
i6 Testing 1 week Mon 09/17/2007 Fri 09/28/2007 Mon 09/17/2007 Fri 10/02/2007 Validation Testing & Documentation Extended test pass by 1 week
Iteration 7 7.5 weeks Mon 10/03/2007 Fri 11/23/2007 Mon 10/03/2007 Mon 11/26/2007
i7 Development 5.5 weeks Mon 10/03/2007 Fri 11/09/2007 Mon 10/03/2007 Fri 11/09/2007 Development & Bug Fixes
**High-level designs for i8 Complete** 1 day Mon 11/12/2007 Mon 11/12/2007 Mon 11/12/2007 Mon 11/12/2007 High-level designs and sizings
i7 Testing 2 weeks Mon 11/12/2007 Fri 11/23/2007 Mon 11/12/2007 Mon 11/26/2007 Validation Testing & Documentation
Iteration 8 9 weeks Mon 11/26/2007 Fri 01/25/2008 Mon 11/26/2007 Fri 01/25/2008
i8 Development 6 weeks Mon 11/26/2007 Fri 01/11/2008 Mon 11/26/2007 Fri 01/11/2008 Development & Bug Fixes
**High-level designs for i9 Complete** 1 day Fri 01/18/2008 Fri 01/18/2008 High-level designs and sizings
i8 Testing 2 weeks Mon 01/14/2008 Fri 01/25/2008 Mon 01/14/2008 Fri 01/25/2008 Validation Testing & Documentation
Iteration 9 6 weeks Mon 01/28/2008 Fri 03/07/2008 Mon 01/28/2008 Fri 03/07/2008
i9 Development 4 weeks Mon 01/28/2008 Wed 02/20/2008 Mon 01/28/2008 Wed 02/20/2008 Development & Bug Fixes
**High-level designs for i10 Complete** 1 day Fri 02/22/2008 Fri 02/22/2008 High-level designs and sizings
i9 Testing 2 weeks Mon 02/25/2008 Fri 03/07/2008 Mon 02/25/2008 Fri 03/07/2008 Validation Testing & Documentation
**Milestone 2** 1 day Fri 03/07/2008 Fri 03/07/2008 Fri 03/07/2008 Fri 03/07/2008 Available for POCs
Iteration 10 8 weeks Mon 03/10/2008 Fri 05/02/2008 Mon 03/10/2008
i10 Development 6 weeks Mon 03/10/2008 Wed 04/16/2008 Mon 03/10/2008 Development & Bug Fixes
**High-level designs for i11 Complete** 1 day Fri 04/18/2008 Fri 04/18/2008 High-level designs and sizings
i10 Testing 2 weeks Mon 04/21/2008 Fri 05/02/2008 Validation Testing & Documentation
Iteration 11 8 weeks Mon 05/05/2008 Fri 06/27/2008
i11 Development 5 weeks Mon 05/05/2008 Wed 06/04/2008 Development & Bug Fixes
i11 Testing 3 weeks Mon 06/09/2008 Fri 06/27/2008 Validation Testing & Documentation
**Milestone 3** 1 day Fri 06/27/2008 Fri 06/27/2008 Available for PoCs
Iteration 12 6 weeks Mon 06/30/2008 Fri 08/08/2008
i12 Development 4 weeks Mon 06/30/2008 Wed 07/23/2008 Development & Bug Fixes
**High-level designs for i13 Complete** 1 day Fri 07/25/2008 Fri 07/25/2008 High-level designs and sizings
i12 Testing 2 weeks Mon 07/28/2008 Fri 08/08/2008 Validation Testing & Documentation
COSMOS 0.9 Availability 1 day Fri 08/08/2008 Fri 08/08/2008 0.9 Release
Iteration 13 6 weeks Mon 08/11/2008 Fri 09/19/2008
i13 Development 4 weeks Mon 08/11/2008 Wed 09/03/2008 Development & Bug Fixes
i13 Testing 2 weeks Mon 09/08/2008 Fri 09/19/2008 Validation Testing & Documentation
Iteration 14 8 weeks Mon 09/22/2008 Fri 11/14/2008
i14 Development 5 weeks Mon 09/22/2008 Wed 10/22/2008 Development & Bug Fixes
i14 Testing 3 weeks Mon 10/27/2008 Fri 11/14/2008 Final Validation Testing, Documentation & Shutdown
COSMOS 1.0 Availability 1 day Fri 11/14/2008 Fri 11/14/2008 GA Release

Release Themes

The COSMOS project adopted the following themes which represent the key focus areas for COSMOS enhancements in the year ahead.

  • Provide an open platform that is standards-based for extensibility and openness
  • Provide exemplary tools for monitoring and management of popular open distributed platforms
  • Establish base framework:
    • Data collection normalization and persistence framework
    • CMDB Federation (CMDBf) support framework
    • Validation/Editing/Viewing framework based on Service Modeling Language (SML)
    • Deployment framework for management enablement using Solution Deployment Descriptor (SDD)

Project Designs

<NEEDS TO BE UPDATED>

The COSMOS project is comprised of four projects, managed in a coordinated fashion, across which the plan items are allocated. COSMOS projects include:

  • Data Collection Project - The COSMOS Data Collection framework aims to provide value by building a standard based integration framework that can incrementally replace the existing ad hoc integrations between agent infrastructures and the management applications that utilize them. The initial focus of the data collection component is the delivery of a framework that provides a well-defined set of service interface types that facilitate the discovery and control of monitoring agents as well as related data services such as collection, transformation, filtering, persistence, and query. These services may be discovered, explored, and controlled through Web Services Distributed Management (WSDM) standard interfaces. They will describe themselves by exposing Service Modeling Language Interchange Format (SML-IF) models using WS-metadata exchange.
  • Data Visualization Project (Design Document)- The COSMOS Data Visualization framework aims to provide value by building a standards based integration infrastructure that provides access to two dimensions of the COSMOS management architecture, COSMOS Data Collection and COSMOS Resource Modeling. COSMOS Data Visualization provides a well-defined set of service interface types that facilitate the exploration of the COSMOS Resource Modeling's repository of models and the retrieval of the COSMOS Data Collection's repository of state, event, and performance information. The model repository is semantically linked to the information in the monitor data repository. This relationship, which is managed in Service Modeling Language (SML) through the Resource Modeling component, is used to connect the exploration of the model with data that has been collected.
  • Resource Modeling Project - The COSMOS Resource Modeling sub-project aims to provide support for building a common model to represent the information being shared in a system management scenario. The project is proposing to use Service Modeling Language (SML) as the XML schema language to define this common model. The SML-IF interchange format will be used to share model components between the tools involved in a system management activity.
  • Management Enablement - To be implemented in a future release

Designs for these projects will be checked in to the COSMOS bugzilla database so that developers can reference them as they create designs for specific plan items.

Features

Plan items targeted for this release represent the addition of new features or areas where existing features will be significantly reworked or enhanced. Plan items are allocated to the projects indicated above.

Milestone 1 Objectives (i1 - i4)

  • Provide tools that support systems management data conforming to the Service Modeling Language (SML) and SML-Interchange Format (SML-IF) standards, including SML and SML-IF document validation, SML-IF editing, import of SML-IF documents and export to SML-IF documents
  • Create example data center described in SML format
  • Provide standard APIs for accessing COSMOS data from heterogeneous clients
  • Create data collectors that gather data from Common Base Event (CBE) logs, JMX, and WSDM Event Format (WEF) sources
  • Provide preset reports to visualize event and statistical data
  • Create a data store to persist statistical information based on the standard SDMX specification
  • Create a relational data store for the persistence of event information and statistical information
  • Create a web-based viewer composed of Web 2.0 gadgets to thoroughly examine data from SML-IF documents
  • Provide extension points to create complementary visualizations in the form of Web 2.0 gadgets and BIRT reports


COSMOS Milestone 1 Plan Items

Milestone 2 Objectives (i5 - i9)

  • Provide framework for implementing CMDBf query and registration services
  • Create Eclipse-integrated toolkit for creating data managers and management data repositories (MDRs)
  • Provide ability to register an MDR with the COSMOS framework
  • Provide ability to register and deregister an MDR with a federating CMDB, using the COSMOS UI
  • Provide ability to query an MDR from the COSMOS UI, using query builder driven by CMDBf metadata
  • Create example MDRs, including a simplistic one and one based on the example data center
  • Provide ability to visualize a CMDBf query response
  • Provide support for deploying to J2EE environments (for example, Tomcat)
  • Provide full test suite showing implementation examples


COSMOS Milestone 2 Use Cases

Milestone 3 Objectives (i10 - i11)

  • Update SML Validator to align with latest SML specification
  • Enhance CMDB Federation Toolkit
  • Provide support for non-COSMOS MDRs and clients using vanilla web services
  • Provide overall quality and stabilization improvements and reduce defect backlog
  • Establish clear set of public APIs & complete externalization of strings


COSMOS Milestone 3 Use Cases

Milestone 4/COSMOS 1.0 GA Objectives (i12-i14)

  • Provide SDD Tooling and Runtime for management enablement
  • Finalize API
  • Enhance quality and documentation



Proposal for Themes - i11 - i13

From Ruth Lee:

My proposal for the COSMOS iterations between now and November is (Themes in italics):

i11: Quality and Extensibility: identify API, document API, drive more adoption, ideally get more activity on the mailing list and newsgroup. Purpose: Increase adoption of COSMOS, stabilize COSMOS, and prove COSMOS as an extensible framework.

i12: Accessibility, internationalization and localization, upgrade path Purpose: Provide support for the pervasive themes in Eclipse. (Suspect this is needed to qualify releasing a 1.0.)

i13: Quality: Reduce defect backlog, finish any items needed to release a 1.0 Purpose: Wind-down, clean up any remaining items that we think are needed to quality to release 1.0 in November.

Delineation between M3 and 1.0: M3 is English-only, non-accessible. 1.0 will be enabled for translation (although nothing will be translated), it will be globalized, accessible, and the upgrade path plan will be in place.