Difference between revisions of "Paho/MQTT Interop Testing Day/Meeting Minutes Nov 4"
m |
|||
(One intermediate revision by the same user not shown) | |||
Line 17: | Line 17: | ||
** Multiple servers bridged together | ** Multiple servers bridged together | ||
* Goal of the testing will be to create a report showing the successful interoperability between different products. | * Goal of the testing will be to create a report showing the successful interoperability between different products. | ||
+ | |||
+ | 3. Schedule | ||
+ | |||
+ | * Dec. 1: start promoting the event and recruiting participants. Ensure we have the wiki page up to date and in a state that it will communicate the goals, objectives and reason to participate. Ian S. will be responsible for recruitment and promotion | ||
+ | * mid-Jan or before: draft test cases made available. Ian C will be responsible for test cases. | ||
+ | * Feb 1: First phone call with participants to discuss preparation requirements to be completed before the testing day. | ||
+ | * March 17: Testing day at EclipseCon |
Latest revision as of 13:17, 10 December 2013
Meeting Minutes - Nov 4, 2013
1. Review logistics
- Assumption is maximum 20 different 'products' will participate, minimum 10. Suggest to limit 2 attendees per product.
- Ian S will secure a room at EclipseCon for Monday, March 17. Room will be setup to have 10 different work areas to support pair-wise testing.
- Internet access is always a challenge so we need to make sure we can do testing without direct access.
- Participation will be free for conference attendees. However non-EclipseCon attendees might have to pay a fee to cover the F&B cost.
2. Suggested agenda items
- Update on standard efforts by TC chairs
- Most of the day will be a series of testing sessions between the participants. Types of testing will include the following:
- Pair-wise testing between a client product and a server product
- Multiple different clients testing against a server
- Multiple servers bridged together
- Goal of the testing will be to create a report showing the successful interoperability between different products.
3. Schedule
- Dec. 1: start promoting the event and recruiting participants. Ensure we have the wiki page up to date and in a state that it will communicate the goals, objectives and reason to participate. Ian S. will be responsible for recruitment and promotion
- mid-Jan or before: draft test cases made available. Ian C will be responsible for test cases.
- Feb 1: First phone call with participants to discuss preparation requirements to be completed before the testing day.
- March 17: Testing day at EclipseCon