+ | = Release plan = | ||
+ | |||
+ | {{warning|Tentative Release plan}} | ||
+ | |||
+ | Mihini has a stable release every 6 month. | ||
+ | |||
+ | Every major release is maintained for 9 months: | ||
+ | |||
+ | *SR1 is "stable"+3 months, | ||
+ | *SR2 is "stable"+6 months, | ||
+ | *SR3 is "stable"+9 months. | ||
+ | |||
+ | Milestones allow to commit on delivering most priority features and bug fixes first, and move towards stabilization when reaching Release Candidates. | ||
+ | |||
+ | == Release calendar == | ||
+ | |||
+ | {{warning|Tentative calendar}} | ||
+ | |||
+ | {| border="1" cellpadding="20" cellspacing="0" | ||
+ | |- | ||
+ | ! | ||
+ | ! 0.8 | ||
+ | ! 0.9 | ||
+ | ! 1.0 | ||
+ | |- | ||
+ | | M1 | ||
+ | | 19-Apr-13 | ||
+ | | 23-Aug-13 | ||
+ | | 21-Feb-14 | ||
+ | |- | ||
+ | | M2 | ||
+ | | *skipped* | ||
+ | | 4-Oct-13 | ||
+ | | 4-Apr-14 | ||
+ | |- | ||
+ | | RC1 | ||
+ | | 10-May-13 | ||
+ | | 15-Nov-13 | ||
+ | | 6-May-14 | ||
+ | |- style="font-weight:bold;" | ||
+ | | final | ||
+ | | 31-May-13 | ||
+ | | 6-Dec-13 | ||
+ | | 6-Jun-14 | ||
+ | |- | ||
+ | | colspan="4" | Maintenance releases | ||
+ | |- | ||
+ | | SR1 | ||
+ | | 30-Aug-13 | ||
+ | | TBD | ||
+ | | TBD | ||
+ | |- | ||
+ | | SR2 | ||
+ | | 29-Nov-13 | ||
+ | | TBD | ||
+ | | TBD | ||
+ | |- | ||
+ | | SR3 | ||
+ | | 28-Feb-14 | ||
+ | | TBD | ||
+ | | TBD | ||
+ | |} |
Revision as of 06:29, 12 March 2013
Release plan
Mihini has a stable release every 6 month.
Every major release is maintained for 9 months:
- SR1 is "stable"+3 months,
- SR2 is "stable"+6 months,
- SR3 is "stable"+9 months.
Milestones allow to commit on delivering most priority features and bug fixes first, and move towards stabilization when reaching Release Candidates.
Release calendar
0.8 | 0.9 | 1.0 | |
---|---|---|---|
M1 | 19-Apr-13 | 23-Aug-13 | 21-Feb-14 |
M2 | *skipped* | 4-Oct-13 | 4-Apr-14 |
RC1 | 10-May-13 | 15-Nov-13 | 6-May-14 |
final | 31-May-13 | 6-Dec-13 | 6-Jun-14 |
Maintenance releases | |||
SR1 | 30-Aug-13 | TBD | TBD |
SR2 | 29-Nov-13 | TBD | TBD |
SR3 | 28-Feb-14 | TBD | TBD |