− | ... | + | [http://www.eclipse.org/cosmos/ COSMOS Project Home] > [[COSMOS|COSMOS Wiki]] > [[COSMOS_Documents|COSMOS Documents]] > |
+ | |||
+ | |||
+ | == COSMOS Project Plan (Draft) == | ||
+ | |||
+ | |||
+ | == COSMOS RELEASE SCHEDULE FOR 2007 == | ||
+ | |||
+ | Link to Europa Release: http://wiki.eclipse.org/index.php/Europa_Simultaneous_Release | ||
+ | |||
+ | {| style="width:75%; height:100px" border="1" | ||
+ | |- | ||
+ | ! style="background:#efefef;"| Milestone/Task || style="background:#efefef;"|Planned Start || style="background:#efefef;"|Planned End || style="background:#efefef;"|Actual Start || style="background:#efefef;"|Actual End || style="background:#efefef;"|% Complete || style="background:#efefef;"|Comments | ||
+ | |- | ||
+ | |Iteration 1-3 definition || 01/01/07 || 03/19/07 || - || - || - || on track | ||
+ | |- | ||
+ | |Iteration 1 demo development || 01/01/07|| 02/23/07 || - || - || - || on track | ||
+ | |- | ||
+ | |Release 1 requirement priority || 03/05/07 || 03/19/07 || - || - || - || on track | ||
+ | |- | ||
+ | |Release vote by community || 03/05/07 || 03/23/07 || - || - || - || on track | ||
+ | |- | ||
+ | |Release 1 plan closure || 03/20/07 || 03/30/07 || - || - || - || on track | ||
+ | |- | ||
+ | |Iteration 2 development and test || 02/23/07 || 04/06/07 || - || - || - || at risk | ||
+ | |- | ||
+ | |Iteration 3 development and test || 04/01/07 || 05/18/07 || - || - || - || - | ||
+ | |- | ||
+ | |Iteration 4 development and test || 05/01/07 || 06/15/07 || - || - || - || - | ||
+ | |- | ||
+ | |Code Freeze || 06/01/07 || 06/23/07 || - || - || - || - | ||
+ | |- | ||
+ | |Europa GA || 06/29/07 || 06/29/07 || - || - || - || to ship alongside | ||
+ | |} | ||
+ | |||
+ | |||
+ | * Iteration 1; Code Freeze 2/28. Iteration 1 complete March 05. (demo) | ||
+ | ** http://wiki.eclipse.org/index.php/COSMOSWeeklyProjectPlan | ||
+ | * Iteration 2: Complete iteration 2 by 4/16. (need i2 plan) | ||
+ | * Iteration 3: Complete iteration 3 by 5/28 (need i3 plan) to ship along with Europa. |
Latest revision as of 17:57, 2 April 2007
COSMOS Project Home > COSMOS Wiki > COSMOS Documents >
COSMOS Project Plan (Draft)
COSMOS RELEASE SCHEDULE FOR 2007
Link to Europa Release: http://wiki.eclipse.org/index.php/Europa_Simultaneous_Release
Milestone/Task | Planned Start | Planned End | Actual Start | Actual End | % Complete | Comments |
---|---|---|---|---|---|---|
Iteration 1-3 definition | 01/01/07 | 03/19/07 | - | - | - | on track |
Iteration 1 demo development | 01/01/07 | 02/23/07 | - | - | - | on track |
Release 1 requirement priority | 03/05/07 | 03/19/07 | - | - | - | on track |
Release vote by community | 03/05/07 | 03/23/07 | - | - | - | on track |
Release 1 plan closure | 03/20/07 | 03/30/07 | - | - | - | on track |
Iteration 2 development and test | 02/23/07 | 04/06/07 | - | - | - | at risk |
Iteration 3 development and test | 04/01/07 | 05/18/07 | - | - | - | - |
Iteration 4 development and test | 05/01/07 | 06/15/07 | - | - | - | - |
Code Freeze | 06/01/07 | 06/23/07 | - | - | - | - |
Europa GA | 06/29/07 | 06/29/07 | - | - | - | to ship alongside |
- Iteration 1; Code Freeze 2/28. Iteration 1 complete March 05. (demo)
- Iteration 2: Complete iteration 2 by 4/16. (need i2 plan)
- Iteration 3: Complete iteration 3 by 5/28 (need i3 plan) to ship along with Europa.