Difference between revisions of "Planning Council/February 03 2010"
(→Tracking progress and compliance) |
(→Late M5 builds!?) |
||
(11 intermediate revisions by the same user not shown) | |||
Line 28: | Line 28: | ||
| John Arthorne | | John Arthorne | ||
| Eclipse (PMC) | | Eclipse (PMC) | ||
− | | | + | | Y |
|- | |- | ||
| Oliver Cole | | Oliver Cole | ||
| Tptp (PMC) | | Tptp (PMC) | ||
− | | | + | | Y |
|- | |- | ||
| Brian Payton | | Brian Payton | ||
Line 44: | Line 44: | ||
| Anthony Hunter | | Anthony Hunter | ||
| Tools (PMC) | | Tools (PMC) | ||
− | | | + | | Y |
|- | |- | ||
| Oisin Hurley | | Oisin Hurley | ||
| Stp (PMC) | | Stp (PMC) | ||
− | | | + | | Y |
|- | |- | ||
| Ed Merks | | Ed Merks | ||
| Modeling (PMC) | | Modeling (PMC) | ||
− | | | + | | Y |
|- | |- | ||
| Thomas Watson | | Thomas Watson | ||
| Rt (PMC) | | Rt (PMC) | ||
− | | | + | | Y |
|- | |- | ||
| David Williams | | David Williams | ||
| WTP (PMC) (appointed Chair) | | WTP (PMC) (appointed Chair) | ||
− | | | + | | Y |
|- | |- | ||
| Gary Xue | | Gary Xue | ||
Line 73: | Line 73: | ||
| Cedric Brun | | Cedric Brun | ||
| OBEO (Strategic Developer) | | OBEO (Strategic Developer) | ||
− | | | + | | Y |
|- | |- | ||
| Stefan Daume | | Stefan Daume | ||
Line 81: | Line 81: | ||
| Neil Hauge | | Neil Hauge | ||
| Oracle (Strategic Developer) | | Oracle (Strategic Developer) | ||
− | | | + | | Y |
|- | |- | ||
| Kaloyan Raev | | Kaloyan Raev | ||
| SAP AG (Strategic Developer) | | SAP AG (Strategic Developer) | ||
− | | | + | | Y |
|- | |- | ||
| Markus Knauer | | Markus Knauer | ||
Line 102: | Line 102: | ||
| Wayne Beaton | | Wayne Beaton | ||
| Eclipse Foundation (appointed) | | Eclipse Foundation (appointed) | ||
− | | | + | | Y |
|- | |- | ||
| Mike Milinkovich | | Mike Milinkovich | ||
Line 145: | Line 145: | ||
== Helios == | == Helios == | ||
− | + | === Exceptions for post-M4 === | |
− | + | * LinuxTools | |
− | * | + | * EEF |
+ | * EGit | ||
+ | * Riena | ||
+ | === Exceptions for post-M5 === | ||
+ | * Sequoyah | ||
+ | * Jetty | ||
* Heads up for Exception coming for Market Place Client ({{bug|296131}}) | * Heads up for Exception coming for Market Place Client ({{bug|296131}}) | ||
− | + | === Late M5 builds!? === | |
− | :: Platform. John? | + | : And what are we going to do about them? |
− | :: EMF. Ed? | + | ::''It was agreed in meeting to advocate "warm up" builds beginning at least the week (or two) before +0. This has the advantage that others, less comfortable with .build files and P2 repositories, can do their own warm up build (or, early testing) before their deadline. This may, however, sometimes "break" the build if higher level items have to adjust their prereq versions, or similar. [revisit in postmortem to explore better ways than '+0, +1, +2]'' |
− | * | + | * Platform. John? |
+ | ::''Build was done on time, but tests take a long time to finish. [good case for warm up builds to start on Helios, without necessarily final bits. Plus, good time for reminder that "meeting deadline" means build is done, tests are done, all votes in, builds promoted, and and ep.build file updated.''] | ||
+ | * EMF. Ed? | ||
+ | ::''Unexpected, or poorly communicated, loss of member who used to do the builds. A replacement has been found, but will take some time to ramp up''. | ||
+ | *'''In all cases of a missed deadline, it is essential to keep everyone informed on cross-project list, or else others end up thinking deadline was met, and may have to do extra debugging, re-work, or re-builds, etc. thus compounding the problem that could have been avoided with just a little better communication.''' | ||
− | === | + | === Cross-Project Teams === |
==== Aggregation ==== | ==== Aggregation ==== | ||
Line 165: | Line 174: | ||
==== Structure of Common Discovery Site ==== | ==== Structure of Common Discovery Site ==== | ||
+ | |||
+ | ''Due to lack of interest or volunteers, it was decided to drop this item, and what we have must be good enough.'' | ||
:users vs. extenders (minimum runtimes vs. SDKs) | :users vs. extenders (minimum runtimes vs. SDKs) | ||
Line 175: | Line 186: | ||
==== Tracking progress and compliance ==== | ==== Tracking progress and compliance ==== | ||
− | :[[Planning Council/Cross Project Teams/Tracking]] | + | :[[Planning Council/Cross Project Teams/Tracking]] |
− | ::me, gabe, and wayne have meetings once a week to check on progress | + | ::me, gabe, and wayne have meetings once a week to check on progress. Sample: [[Image:Screenshot-1.png]] |
+ | |||
+ | ::Interim Plan: provide "check list style" version of requirements, similar to [http://www.eclipse.org/helios/planning/EclipseSimultaneousReleaseFormPrototype.html original sample prototype] | ||
+ | |||
+ | ::Backup Plan? | ||
+ | :::xml files? (that can be transformed to pretty web page reports | ||
+ | |||
+ | ::''Wayne did not have any additional information, but said he would check with Gabe. It is "high priority", but still under "EclipseCon work". '' | ||
+ | |||
+ | ::''Backup Plan C: revert to bugzilla'' | ||
== Other business == | == Other business == | ||
* Propose face-face EclipseCon meeting 2:00 (local time) on the Sunday before EclispeCon (3/21)? | * Propose face-face EclipseCon meeting 2:00 (local time) on the Sunday before EclispeCon (3/21)? | ||
+ | |||
+ | ::''Confirmed (there was no clear alternative, so "like last year" seems best course). '' | ||
== ToDo Items == | == ToDo Items == | ||
Line 191: | Line 213: | ||
*provide concrete instructions for (new) license-consistency requirement (John Arthorne). | *provide concrete instructions for (new) license-consistency requirement (John Arthorne). | ||
+ | |||
+ | *add automatic tests (e.g. non-api scans, layouts, presence of BREE, versioning, signed, etc.) | ||
== Next Meeting == | == Next Meeting == | ||
− | + | ||
− | :[[Planning_Council/ | + | :[[Planning_Council/March_03_2010|March 3, Wednesday]], Noon Eastern Time. |
− | + | ||
== Reference == | == Reference == |
Latest revision as of 17:03, 3 February 2010
Contents
Logistics
Meeting Title: | Planning Council Conference Call |
Date & Time: | Wednesday, February 03, 2010, at 1700 UTC / 0900 SFO / 1200 NYC / 1700 London / 1800 Berlin |
Dial-in: | For the call-in numbers, see the "Project Review" number on Foundation Portal page. |
Attendees
PMC (and Strategic) Reps
Strategic Reps
Appointed
|
Inactive
|
Galileo
Any SR2 issues?
Helios
Exceptions for post-M4
- LinuxTools
- EEF
- EGit
- Riena
Exceptions for post-M5
- Sequoyah
- Jetty
- Heads up for Exception coming for Market Place Client (bug 296131)
Late M5 builds!?
- And what are we going to do about them?
- It was agreed in meeting to advocate "warm up" builds beginning at least the week (or two) before +0. This has the advantage that others, less comfortable with .build files and P2 repositories, can do their own warm up build (or, early testing) before their deadline. This may, however, sometimes "break" the build if higher level items have to adjust their prereq versions, or similar. [revisit in postmortem to explore better ways than '+0, +1, +2]
- Platform. John?
- Build was done on time, but tests take a long time to finish. [good case for warm up builds to start on Helios, without necessarily final bits. Plus, good time for reminder that "meeting deadline" means build is done, tests are done, all votes in, builds promoted, and and ep.build file updated.]
- EMF. Ed?
- Unexpected, or poorly communicated, loss of member who used to do the builds. A replacement has been found, but will take some time to ramp up.
- In all cases of a missed deadline, it is essential to keep everyone informed on cross-project list, or else others end up thinking deadline was met, and may have to do extra debugging, re-work, or re-builds, etc. thus compounding the problem that could have been avoided with just a little better communication.
Cross-Project Teams
Aggregation
Planning Council/Cross Project Teams/Aggregation
Status: me, john, and thomas meeting on Friday
Structure of Common Discovery Site
Due to lack of interest or volunteers, it was decided to drop this item, and what we have must be good enough.
- users vs. extenders (minimum runtimes vs. SDKs)
- runtime targets vs. tools
- hierarchical categories (are more levels required?)
Anyone care? Any volunteers? (If not ... and you leave it up to me ... you know what's going to happen, right?)
Tracking progress and compliance
- Interim Plan: provide "check list style" version of requirements, similar to original sample prototype
- Backup Plan?
- xml files? (that can be transformed to pretty web page reports
- Backup Plan?
- Wayne did not have any additional information, but said he would check with Gabe. It is "high priority", but still under "EclipseCon work".
- Backup Plan C: revert to bugzilla
Other business
- Propose face-face EclipseCon meeting 2:00 (local time) on the Sunday before EclispeCon (3/21)?
- Confirmed (there was no clear alternative, so "like last year" seems best course).
ToDo Items
(volunteers welcome)
- create (and update) helios container plan (Wayne (re) volunteered)
- coordinate community input for next year's name (Oliver says last year this was started "shortly before EclipseCon" ... so, no rush).
- provide concrete instructions for (new) license-consistency requirement (John Arthorne).
- add automatic tests (e.g. non-api scans, layouts, presence of BREE, versioning, signed, etc.)
Next Meeting
- March 3, Wednesday, Noon Eastern Time.
Reference
Simultaneous Release Roles and Simultaneous Release Roles/EMO