Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "Swordfish Documentaion: Sprint Plan"
(Add milestone picture) |
(add wikipedia link to scrum method) |
||
Line 7: | Line 7: | ||
− | Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project. The Features and Tasks for Each sprint can be accessed through the links below: | + | Swordfish is developed using the [http://en.wikipedia.org/wiki/Scrum_(development) scrum method]. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project. The Features and Tasks for Each sprint can be accessed through the links below: |
[[Swordfis_Documentation:_Galileo_Sprint1 | sprint1: 09.02.2009 – 05.03.2009]] | [[Swordfis_Documentation:_Galileo_Sprint1 | sprint1: 09.02.2009 – 05.03.2009]] |
Revision as of 11:50, 9 February 2009
{{#eclipseproject:rt.swordfish}}
Swordfish Sprints for Galileo
Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project. The Features and Tasks for Each sprint can be accessed through the links below:
sprint1: 09.02.2009 – 05.03.2009
sprint2: 06.03.2009 – 18.03.2009 (M6)
sprint3: 19.03.2009 – 02.04.2009
sprint4: 03.04.2009 – 16.04.2009
sprint5: 17.04.2009 – 06.05.2009 (M7)
sprint6: 07.05.2009 – 20.05.2009 (RC1)
Release: 21.05.2009 – 17.06.2009 (Endgame)