Cosmos Release Plan 1.1
Contents
COSMOS 1.1 Release Plan
Overview
Please send comments about this plan to the cosmos-mgmt@eclipse.org project management mailing list.
This document lays out the feature and API set for the COSMOS releases.
This plan describes the deliverables, milestones, and plan items for the COSMOS project. Each plan item covers a feature or API that is to be added to COSMOS, or some aspect of COSMOS that is to be improved. Each plan item has its own entry in the COSMOS bugzilla database, with a title and a concise summary (usually a single paragraph) that explains the work item at a suitably high level so that everyone can readily understand the work item.
Release Deliverables
The following release deliverables are provided:
- Runtime
- Tooling
- Source
- Examples
- Component Tests
- Data Collection Implementation
- Data Visualization Implementation
- Resource Modeling Implementation
- Management Enablement Implementation
- CMDBf Implementation
Release Milestones
This COSMOS 1.1 is targeted for general availability on 25-September-2009. All deliverables will be available for download as soon as the release has been tested and validated in the target configurations. There is an allocation of resource to defect removal in all iterations. The first Iterations 1-2 will contain the bulk of the enhancement work, with Iteration 3 stabilizing the milestone driver, with Iterations 4, 5 and 6 will be devoted to fleshing out the framework, and Iteration 7 will mainly be used to stabilize and shut down the release. There is a one week buffer after I7 to the GA date in order to plan and prep for the release review.
Milestone | Duration | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Description | Comments | |
Iteration 1 | 8 weeks | Nov-17-2008 | Jan-09-2009 | Enhancements | ||||
i1 Development | 5 weeks | Nov-17-2008 | Dec-17-2008 | Development & bug fixes | ||||
i1 Testing | 3 weeks | Dec-22-2008 | Jan-09-2009 | Validation Testing | ||||
Iteration 2 | 6 weeks | Jan-12-2009 | Feb-20-2009 | Enhancements | ||||
i2 Development | 4 weeks | Jan-12-2009 | Feb-04-2009 | Development & bug fixes | ||||
i2 Testing | 2 weeks | Feb-09-2009 | Feb-20-2009 | Validation Testing | ||||
Iteration 3 | 8 weeks | Feb-23-3009 | Apr-03-2009 | Stabilize | ||||
i3 Development | 4 weeks | Feb-23-2009 | Mar-18-2009 | Development & bug fixes | ||||
i3 shutdown phase | 2 weeks | Mar-19-2009 | Apr-01-2009 | Approved changes only: documentation, examples, defects that stabilize the driver, write new tests. Before checking in anything, a project lead must review and approve that change. | ||||
i3 Testing | 2 weeks | Apr-06-2009 | Apr-17-2009 | Validation Testing | ||||
Milestone driver | 1 day | Apr-17-2009 | Apr-17-2009 | Available for POCs | ||||
Iteration 4 | 4 weeks | Apr-20-2009 | May-15-2009 |
Enhancements | ||||
i4 Development | 2 weeks | Apr-20-2009 | Apr-29-2009 | Development & bug fixes | ||||
i4 Testing | 2 weeks | May-04-2009 | May-15-2009 | Validation Testing | ||||
Iteration 5 | 6 weeks | May-18-2009 | June-26-2009 |
Enhancements | ||||
i5 Development | 4 weeks | May-18-2009 | June-10-2009 | Development & bug fixes | ||||
i5 Testing | 2 weeks | June-15-2009 | June-26-2009 | Validation Testing | ||||
Iteration 6 | 6 weeks | June-29-2009 | August-7-2009 |
Enhancements |
| |||
i6 Development | 4 weeks | June-29-2009 | July-24-2009 | Development & bug fixes | ||||
i6 Testing | 2 weeks | July-27-2009 | August-7-2009 | Validation Testing | ||||
Iteration 7 | 6 weeks | August-10-2009 | September-18-2009 |
Stabilize |
| |||
i7 Development | 4 weeks | August-10-2009 | September-4-2009 | Development & bug fixes | ||||
i7 Testing | 2 weeks | September-7-2009 | September-18-2009 | Validation Testing | ||||
COSMOS 1.1 availability | 1 day | September-25-2009 | September-25-2009 | GA Release |
See 259011 for details on how those release review dates were calculated. They are tentative and may change.
Major deliverables
- SML bug fixes
- reconciliation taxonomy
- finish the SDD tooling for the BTG
- have our SDD runtime driver for conformance level 1
- stabilize CMDBf support
- move SML out of research
- move SDD out of research
Features
Plan items targeted for this release represent the addition of new features or areas where existing features will be significantly reworked or enhanced. Plan items are allocated to the projects indicated above.
Milestone 1 Objectives (i1 - i3)
- v1.1 Iteration 1 Plan
- v1.1 Iteration 1 week 1 test status - not collected
- v1.1 Iteration 1 week 2 test status - not collected
- v1.1 Iteration 1 week 3 test status - not collected
- v1.1 Iteration 1 week 4 test status
- v1.1 Iteration 1 week 5 test status
- v1.1 Iteration 1 test pass
- v1.1 Iteration 2 Plan
- v1.1 Iteration 3 Plan
- v1.1 Iteration 2 week 1 test status - not collected
- v1.1 Iteration 3 week 2 test status
- v1.1 Iteration 3 week 3 test status
- v1.1 Iteration 3 week 4, 5, and 6 test status
- v1.1 Iteration 3 test pass