=== Announcements And Special Reports  ===
 
=== Announcements And Special Reports  ===
  
* Congratulations to Kaloyan for becoming a committer on the WTP releng project.
+
 
  
 
=== WTP Calendar  ===
 
=== WTP Calendar  ===
Line 67: Line 67:
  
 
* [http://www.eclipse.org/webtools/plans/3.3.1/pmc-bug-approval.php latest PMC approved list]
 
* [http://www.eclipse.org/webtools/plans/3.3.1/pmc-bug-approval.php latest PMC approved list]
 
* PMC review +3 next week (after we declare)
 
  
 
==== 3.3.1 Schedule ====
 
==== 3.3.1 Schedule ====
Line 93: Line 91:
 
* Juno Project planning
 
* Juno Project planning
 
** [http://www.eclipse.org/projects/project-plan.php?projectid=webtools Top level plan]
 
** [http://www.eclipse.org/projects/project-plan.php?projectid=webtools Top level plan]
 
+
** Schedule:
* Schedule:
+
 
*** M2: Initial Planning document.
 
*** M2: Initial Planning document.
 
*** M3: Iterate/Review plans
 
*** M3: Iterate/Review plans
Line 116: Line 113:
  
 
== Other business  ==
 
== Other business  ==
 
* [http://www.eclipse.org/projects/project-plan.php?projectid=webtools WebTools top level plan for Juno:]  Clarification to our commitment supporting 2 platform versions(3.8 and 4.2), using compatible api's and moving to 4.2 as our default platform.
 
 
* Changes coming regarding the webtools.website project.  [http://dev.eclipse.org/mhonarc/lists/wtp-dev/msg08209.html David's mailing list post] regarding how we administer our website and downloads area.
 
  
 
* [http://wiki.eclipse.org/WTP_Git_Migration_Home Git education wiki page] - looking to the future, and encouraging all project leads to start using git tools.
 
* [http://wiki.eclipse.org/WTP_Git_Migration_Home Git education wiki page] - looking to the future, and encouraging all project leads to start using git tools.

Latest revision as of 13:59, 15 September 2011

WTP Development Status Meeting

Remember, any committer can add an agenda item. Typically, short announcements or news items go in the "Announcements" section at the beginning. Longer items or issues requiring discussion should go in the "Other business" section at end.

Announcements And Special Reports

WTP Calendar

(Weekly Google Calendar updated through December, 2011)


For Juno/Indigo overall dates, see the Simultaneous Release Calendar


Focus on Quality (Neil)

  • Focus Item:
  • Target to a specific release or "future" if planning to fix but not in the next release
  • Adjust severity as appropriate

WTP 3.2.5

  • All sub projects required to smoke test this week until end of release


3.2.5 Schedule

9/16 M build - all teams start smoke testing
9/23 M build
9/30 M build
10/7 M build (after this build, begin PMC-review ramp-down (+1 begins))
10/14 M build (after this build, begin +2)
10/21 M build (after this build, begin +3)
10/28 M build final build (with one week of buffer following this week, quiet week, until 11/4 (re-spin would require +3))
11/4 WTP 3.2.5 GA

See "references" [1] for detailed explanation of what these dates mean.

3.2.5 Bug Review

Bugs targeted to 3.2.5

WTP 3.3.1

3.3.1 Schedule

9/16 final M build (with one week of buffer following this week, quiet week, until 9/23 (re-spin would require +3))
9/23 SR1 GA

Bug Review

Bugs targeted to 3.3.1
Hotbugs [2]
Blocker and Critical

WTP 3.4.0

  • latest build
  • Smoke testing on 4.2 platform this week. Carl to mention progress publishing 4.2 based builds.
  • M2 driver next week, so please be careful committing changes next week.


  • Juno Project planning
    • Top level plan
    • Schedule:
      • M2: Initial Planning document.
      • M3: Iterate/Review plans
      • M4: Final Plans due


3.4.0 Schedule

9/16 I build declare
9/23 M2 declare
9/30 Official WTP 3.4.0 M2 availability - no declare

Bug Review

Bugs targeted to 3.4.0
Hotbugs
Blocker and Critical

Other business

Indigo release retrospective

References

  1. Our plan dates are on 'Friday' of the week. But, we produce and test the build on Thursday of the week, and ideally declare on Thursday. The dates in the Google Web Tools group calendar are for 'Thursdays' since that's a calendar for committers. We give ourselves the buffer to Friday, as our "public" date, that others can pick up our build, just in case a regression is found on Thursday and we have to respin and retest. [Technically, some might say, we still have till the following Tuesday or Wednesday for some "Simultaneous Release" due dates ... but it's hard to do much in that window, without disrupting everyone ... so we'll not use that buffer, except for the worst emergencies.]
  2. Hotbug Policy

Also, see

Indigo SR2 Simultaneous Release Schedule
3.3 Rampdown plan
Standard Format Plans
WTP 3.2.x maintenance release plan
how/when to branch code?
IP Logs selector
WTP Helios retrospective.
See also the WTP Meeting Archive-Reference Page.

Copyright © Eclipse Foundation, Inc. All Rights Reserved.