Ramp down for Europa

For reference, see the Europa Simultaneous Release, in particular Europa_Simultaneous_Release#Milestones_and_Release_Candidates

From M6 to RC1 on May 18th, we expect each component lead (or delegate) to review and verify their teams' bugs.

After the first RC is produced, others will be produced, if needed, every week.

  • May 18th, RC 1 produced
After the 18th, besides the normal component team review, at least 1 PMC member must also vote +1 after reviewing the bug for appropriateness and risk.
  • May 25


  • June 1
After June 1, besides the normal component team review, at least 2 PMC members must also vote +1 after reviewing the bug for appropriateness and risk.
  • June 8


  • June 15
After the 15th, besides the normal component team review, at least 3 PMC member must also vote +1 after reviewing the bug for appropriateness and risk.
  • June 22
Begin zip, update, site preparations
  • June 29
release