Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "WTP 2.0 Ramp down Plan for Europa"
(added dates and policies) |
|||
Line 2: | Line 2: | ||
For reference, see the [[Europa Simultaneous Release]], | For reference, see the [[Europa Simultaneous Release]], | ||
− | in particular [[Europa_Simultaneous_Release#Milestones_and_Release_Candidates]] | + | in particular the [[Europa_Simultaneous_Release#Milestones_and_Release_Candidates | Milestones and Release Candidates]] |
From M6 to RC1 on May 18th, we expect each component lead (or delegate) to review and | From M6 to RC1 on May 18th, we expect each component lead (or delegate) to review and | ||
verify their teams' bugs. | verify their teams' bugs. | ||
− | After the first RC is produced, | + | After the first RC is produced, other RCs will be produced, if needed, every week. |
* May 18th, RC 1 produced | * May 18th, RC 1 produced | ||
− | :After the 18th, besides the normal component team review, at least 1 PMC member must also vote +1 after reviewing the bug for appropriateness and risk. | + | :After the 18th, besides the normal component team review, at least 1 PMC member must also review and vote +1 after reviewing the bug for appropriateness and risk. |
* May 25 | * May 25 | ||
Line 18: | Line 18: | ||
* June 1 | * June 1 | ||
− | :After June 1, besides the normal component team review, at least 2 PMC members must also vote +1 after reviewing the bug for appropriateness and risk. | + | :After June 1, besides the normal component team review, at least 2 PMC members must also review and vote +1 after reviewing the bug for appropriateness and risk. |
* June 8 | * June 8 | ||
Line 25: | Line 25: | ||
* June 15 | * June 15 | ||
− | :After the 15th, besides the normal component team review, at least 3 PMC member must also vote +1 after reviewing the bug for appropriateness and risk. | + | :After the 15th, besides the normal component team review, at least 3 PMC member must also review and vote +1 after reviewing the bug for appropriateness and risk. |
* June 22 | * June 22 | ||
− | : | + | :Do zip, update, site preparations |
* June 29 | * June 29 | ||
− | : | + | :Release |
Revision as of 02:50, 4 February 2007
Ramp down for Europa
For reference, see the Europa Simultaneous Release, in particular the Milestones and Release Candidates
From M6 to RC1 on May 18th, we expect each component lead (or delegate) to review and verify their teams' bugs.
After the first RC is produced, other RCs will be produced, if needed, every week.
- May 18th, RC 1 produced
- After the 18th, besides the normal component team review, at least 1 PMC member must also review and vote +1 after reviewing the bug for appropriateness and risk.
- May 25
- June 1
- After June 1, besides the normal component team review, at least 2 PMC members must also review and vote +1 after reviewing the bug for appropriateness and risk.
- June 8
- June 15
- After the 15th, besides the normal component team review, at least 3 PMC member must also review and vote +1 after reviewing the bug for appropriateness and risk.
- June 22
- Do zip, update, site preparations
- June 29
- Release