Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "Virgo/Community/Minutes-2010-05-11"

(New page: == Attendees == *Glyn Normington - VMware *Nikolai Tankov - SAP == Discussion == 1. Follow up on p2 is still pending. Nikolai gave an overview of how p2 will be used to speed up Virgo...)
 
(Discussion)
Line 6: Line 6:
 
== Discussion  ==
 
== Discussion  ==
  
1. Follow up on p2 is still pending. Nikolai gave an overview of how p2 will be used to speed up Virgo startup. Apparently Equinox can restart more reliably when p2 is used to install bundles than when the standard Equinox install mechanism is used.
+
1. Nikolai gave an overview of how p2 will be used to speed up Virgo startup. Apparently Equinox can restart more reliably when p2 is used to install bundles than when the standard Equinox install mechanism is used. The next steps are to protoype the use of p2 to install bundles into vanilla Equinox before integrating the prototype into the Virgo kernel.
  
 
2. The kernel is now checked in and ready for others to build. Development of post-baseline features can proceed on a branch which can be merged back into master after the baseline release.
 
2. The kernel is now checked in and ready for others to build. Development of post-baseline features can proceed on a branch which can be merged back into master after the baseline release.
  
 
3. We are planning to raise all remaining CQs by 21 May 2010. The Eclipse IP are aiming to provide initial approval by 31 May. After that the VMware team will be trying to create a baseline incubator release or milestone, depending upon what is permitted under parallel IP by the Eclipse process.
 
3. We are planning to raise all remaining CQs by 21 May 2010. The Eclipse IP are aiming to provide initial approval by 31 May. After that the VMware team will be trying to create a baseline incubator release or milestone, depending upon what is permitted under parallel IP by the Eclipse process.

Revision as of 09:28, 11 May 2010

Attendees

  • Glyn Normington - VMware
  • Nikolai Tankov - SAP

Discussion

1. Nikolai gave an overview of how p2 will be used to speed up Virgo startup. Apparently Equinox can restart more reliably when p2 is used to install bundles than when the standard Equinox install mechanism is used. The next steps are to protoype the use of p2 to install bundles into vanilla Equinox before integrating the prototype into the Virgo kernel.

2. The kernel is now checked in and ready for others to build. Development of post-baseline features can proceed on a branch which can be merged back into master after the baseline release.

3. We are planning to raise all remaining CQs by 21 May 2010. The Eclipse IP are aiming to provide initial approval by 31 May. After that the VMware team will be trying to create a baseline incubator release or milestone, depending upon what is permitted under parallel IP by the Eclipse process.

Copyright © Eclipse Foundation, Inc. All Rights Reserved.