Line 19: | Line 19: | ||
** checked with Matt about {{bug|173541}}, the defect was deferred to future, and also returned {{bug|194850}} | ** checked with Matt about {{bug|173541}}, the defect was deferred to future, and also returned {{bug|194850}} | ||
** fixed {{bug|219264}}, {{bug|218271}}, {{bug|218875}} and plans to finish {{bug|212040}}, {{bug|212532}} by eod | ** fixed {{bug|219264}}, {{bug|218271}}, {{bug|218875}} and plans to finish {{bug|212040}}, {{bug|212532}} by eod | ||
− | ** worked on {{bug|219845}} and on the related problem with Log | + | ** worked on {{bug|219845}} and on the related problem with regard to the Log Analyzer component backward compatibility issues |
+ | ** didn't have time to review {{bug|212806}} | ||
* Rohit | * Rohit | ||
** fixed {{bug|214785}}, {{bug|219242}}, {{bug|192250}} | ** fixed {{bug|214785}}, {{bug|219242}}, {{bug|192250}} |
Latest revision as of 19:42, 29 February 2008
Contents
Attendees
- Present:
- Alex Nan
- Rohit Shetty
- Hariharan Narayanan
- Yasuhisa Gotoh
- Absent:
- Richard Yun Song Huang - phone problems
4.4.1
- Monitoring project has executed a final smoke test last week and has successfully finished 4.4.1 testing
4.5
- slow progress has been made on defect fixing, we are behind schedule and at risk of not finishing all targeted defects for 4.5 i6
- Alex
- finished assigning defects to weekly schedule
- checked with Matt about bug 173541, the defect was deferred to future, and also returned bug 194850
- fixed bug 219264, bug 218271, bug 218875 and plans to finish bug 212040, bug 212532 by eod
- worked on bug 219845 and on the related problem with regard to the Log Analyzer component backward compatibility issues
- didn't have time to review bug 212806
- Rohit
- fixed bug 214785, bug 219242, bug 192250
- Gotoh-san
- fixed bug 204615
- is investigating bug 204742
- work in progress on bug 207251, bug 184530
- Alex offers to help on bug 184530 and bug 192554
- Hari
- needs to get a closure on bug 180950 ASAP
- needs to address bug 219989
- Richard
- worked on bug 207255
- will start work on bug 211085 and bug 215474
Action items
- team to focus on reducing defect back log, targetting P1 and high severity defects first
- Alex to open a defect for the Log Analyzer component backward compatibility issue (by the time these notes are written bug 220866 was already opened)
- Hari to contact Alex to decide whether MAX manual tests can be automated using AGR bug 180950
- Gotoh-san to finish ASAP symptom test automation bug 207251
- Richard to get a resolution ASAP on bug 207255