Jump to: navigation, search

STP/Archive/STP Ramp-down Plan

< STP‎ | Archive
Revision as of 11:16, 20 February 2008 by Ohurley.iona.com (Talk | contribs)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

This is about structuring our activities in the milestones coming up to Europa. Milestones/RC's are to retain 1 week of bugfixing at the end of the milestone. The final 4 weeks of work is to be dedicated to bugfixing, website and documentary updates and minor usability changes. Starting at post M6 (after April 11), we will be operating things on a tighter basis. Bugzillas to be submitted for all proposed work, and approval for work to go through the PMC, requiring a single +1 to approve.