Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "RT/meetings/PMC Minutes 121003"

< RT‎ | meetings
(New page: == Attendees == == Agenda == * eRCP status? * Planning Meeting (retrospective) * Negative Requirements (A.PDE target hack) * RT projects, LTS and the release train)
 
 
Line 1: Line 1:
 
== Attendees ==
 
== Attendees ==
 +
* Glyn
 +
* Tom
 +
* Ian
  
 
== Agenda ==
 
== Agenda ==
Line 6: Line 9:
 
* Negative Requirements (A.PDE target hack)
 
* Negative Requirements (A.PDE target hack)
 
* RT projects, LTS and the release train
 
* RT projects, LTS and the release train
 +
* Juno SR1 status
 +
 +
== eRCP status ==
 +
* Note sent to ercp-dev mailing list indicating the intent to terminate
 +
** Only one response from a consumer of eRCP voicing concerns about building
 +
** Tom got privately contacted by Eric MF Hsu the last committer of the project.  He agrees it is time to terminate.
 +
 +
== RT projects, LTS and release train ==
 +
* Need to review the note from Glyn and respond
 +
** Briefly looked at the list proposed by Glyn during the call.  Did not disagree with anything on the list and (so far) did not find additional requirements add for RT projects in LTS
 +
 +
== Juno SR1 status ==
 +
* A buckminster fix is needed
 +
* Need to respin SR1 for EPPs only

Latest revision as of 11:21, 3 October 2012

Attendees

  • Glyn
  • Tom
  • Ian

Agenda

  • eRCP status?
  • Planning Meeting (retrospective)
  • Negative Requirements (A.PDE target hack)
  • RT projects, LTS and the release train
  • Juno SR1 status

eRCP status

  • Note sent to ercp-dev mailing list indicating the intent to terminate
    • Only one response from a consumer of eRCP voicing concerns about building
    • Tom got privately contacted by Eric MF Hsu the last committer of the project. He agrees it is time to terminate.

RT projects, LTS and release train

  • Need to review the note from Glyn and respond
    • Briefly looked at the list proposed by Glyn during the call. Did not disagree with anything on the list and (so far) did not find additional requirements add for RT projects in LTS

Juno SR1 status

  • A buckminster fix is needed
  • Need to respin SR1 for EPPs only

Back to the top