=== M1 - 5 August 2011 ===
 
=== M1 - 5 August 2011 ===
 +
 
{{PlanItem|Create 3.8 Plan||Complete}}
 
{{PlanItem|Create 3.8 Plan||Complete}}
  
 
=== M2 - 16 September 2011 ===
 
=== M2 - 16 September 2011 ===
 +
 
{{PlanItem|Prepare 3.7.1 Fixes||Complete}}
 
{{PlanItem|Prepare 3.7.1 Fixes||Complete}}
 
{{PlanItem|Git migration|351001|InProgress}}
 
{{PlanItem|Git migration|351001|InProgress}}
Line 35: Line 37:
 
{{PlanItem|Allow JDT index to be contributed|?|Investigate}}
 
{{PlanItem|Allow JDT index to be contributed|?|Investigate}}
  
=== M6 - 16 March 2012 (API Freeze) ===
+
=== M6 - 16 March 2012 ===
 +
(API Freeze)
  
=== M7 - 5 April 2012 (Feature Freeze) ===
+
=== M7 - 5 April 2012 ===
 +
(Feature Freeze)
  
{{PlanItem|Bug fixing||Investigate}}
+
{{PlanItem|General bug fixing||Investigate}}
  
 
=== RC Builds - May/June 2012 ===
 
=== RC Builds - May/June 2012 ===

Revision as of 11:43, 15 August 2011

Warning2.png
Unofficial Planning Document
This is an unofficial document used by the PDE team to help with the planning process. Items on this list are not guaranteed to be found in a release.


Overview

This is the PDE project plan for the Eclipse Project Juno release.

PDE will focus on testing and releasing on the 4.2 platform. However, all PDE plug-ins will be compatible with both the 3.8 and 4.2 release.

Plan items are listed in the milestone when work is intended to start. Items that take longer than one milestone may be moved after completion. The plan is intentionally heavy on milestones two through five to allow for bug fixing, iterative development, performance and polish work in later milestones.

M1 - 5 August 2011

Ok green.gif Create 3.8 Plan

M2 - 16 September 2011

Ok green.gif Prepare 3.7.1 Fixes

Progress.gif Git migration (351001)

Progress.gif Target platform API to contribute UI (347695)

Glass.gif Ability to filter quick-fixes (322273)

Progress.gif Apply problem filters to use tasks (332772)

M3 - 28 October 2011

Glass.gif Target platform per project (159072)

Glass.gif Performance tests and improvements (334748) - Consider performance impacts of Target per project

Glass.gif Support Java 7 efforts (?)

Glass.gif Provide OSGi tracing page (296631)

Progress.gif Support API compatibility checks against unresolved bundles (271045)

M4 - 9 December 2011

M5 - 27 January 2012

Glass.gif Prepare 3.7.2 Fixes

Glass.gif Replace samples page with p2 effort (353139)

Glass.gif Allow JDT index to be contributed (?)

M6 - 16 March 2012

(API Freeze)

M7 - 5 April 2012

(Feature Freeze)


Glass.gif General bug fixing

RC Builds - May/June 2012

Glass.gif Polish

Glass.gif Performance

Glass.gif Bug fixing

Glass.gif Clean up website and wiki

Glass.gif Update Copyrights

Glass.gif Check for Broken NLS

Glass.gif Doc Pass

Glass.gif Retrospective

Overall Goals

This section will list general goals for the 3.8 release using information from the Retrospective.

Unscheduled Items

This section will list items that we are interested in completing during 3.8 but have not been scheduled. For general ideas, use the Wishlist.