Mihini/Project Plan


Please send comments about this plan to the mihini-dev@eclipse.org developer mailing list.

This document lays out the feature and API set for the feature releases of Mihini.

Project Plan

0.8: You can find more details on the Project Plan discussions for 0.8

Release plan

Tentative Release plan

Mihini has a stable release every 6 month.

Every major release is maintained for 9 months:

  • SR1 is "stable"+3 months,
  • SR2 is "stable"+6 months,
  • SR3 is "stable"+9 months.

Milestones allow to commit on delivering most priority features and bug fixes first, and move towards stabilization when reaching Release Candidates.

Release calendar

Tentative calendar

0.8 0.9 1.0
M1 12-Apr-13 23-Aug-13 21-Feb-14
M2 *skipped* 4-Oct-13 4-Apr-14
RC1 10-May-13 15-Nov-13 6-May-14
final 24-May-13 6-Dec-13 6-Jun-14
Maintenance releases
SR1 30-Aug-13 TBD TBD
SR2 29-Nov-13 TBD TBD
SR3 28-Feb-14 TBD TBD