Difference between revisions of "Mihini/Project Plan"
< Mihini
(→Release Deliverables) |
(→Project Plan) |
||
(6 intermediate revisions by the same user not shown) | |||
Line 4: | Line 4: | ||
This document lays out the feature and API set for the feature releases of Mihini. | This document lays out the feature and API set for the feature releases of Mihini. | ||
− | You can find more details on the [[Mihini/Project Plan/0. | + | = Project Plan = |
+ | |||
+ | *0.8: [[Mihini/Project Plan/0.8|Project Plan discussions for 0.8]] | ||
+ | *0.9: You can find more details on the [[Mihini/Project Plan/0.9|Project Plan discussions for 0.9]] | ||
= Release plan = | = Release plan = | ||
Line 24: | Line 27: | ||
{{warning|Tentative calendar}} | {{warning|Tentative calendar}} | ||
− | {| | + | {| cellspacing="0" cellpadding="20" border="1" |
|- | |- | ||
! | ! | ||
! 0.8 | ! 0.8 | ||
! 0.9 | ! 0.9 | ||
+ | ! 0.10 | ||
! 1.0 | ! 1.0 | ||
|- | |- | ||
| M1 | | M1 | ||
− | | | + | | |
+ | | 05-Jul-2013 | ||
| 23-Aug-13 | | 23-Aug-13 | ||
| 21-Feb-14 | | 21-Feb-14 | ||
|- | |- | ||
| M2 | | M2 | ||
+ | | | ||
| *skipped* | | *skipped* | ||
| 4-Oct-13 | | 4-Oct-13 | ||
Line 42: | Line 48: | ||
|- | |- | ||
| RC1 | | RC1 | ||
− | | | + | | |
+ | | 02-Aug-2013 | ||
| 15-Nov-13 | | 15-Nov-13 | ||
| 6-May-14 | | 6-May-14 | ||
|- style="font-weight:bold;" | |- style="font-weight:bold;" | ||
| final | | final | ||
− | | | + | | 11-Feb-13 |
+ | | 09-Aug-2013 | ||
| 6-Dec-13 | | 6-Dec-13 | ||
| 6-Jun-14 | | 6-Jun-14 | ||
Line 54: | Line 62: | ||
|- | |- | ||
| SR1 | | SR1 | ||
+ | | 15-Apr-13 | ||
| 30-Aug-13 | | 30-Aug-13 | ||
| TBD | | TBD | ||
Line 59: | Line 68: | ||
|- | |- | ||
| SR2 | | SR2 | ||
+ | | 10-Jun-13 | ||
| 29-Nov-13 | | 29-Nov-13 | ||
| TBD | | TBD | ||
Line 64: | Line 74: | ||
|- | |- | ||
| SR3 | | SR3 | ||
+ | | | ||
| 28-Feb-14 | | 28-Feb-14 | ||
| TBD | | TBD | ||
| TBD | | TBD | ||
|} | |} |
Revision as of 05:07, 6 June 2013
Introduction
Please send comments about this plan to the mihini-dev@eclipse.org developer mailing list.
This document lays out the feature and API set for the feature releases of Mihini.
Project Plan
- 0.8: Project Plan discussions for 0.8
- 0.9: You can find more details on the Project Plan discussions for 0.9
Release plan
Mihini has a stable release every 6 month.
Every major release is maintained for 9 months:
- SR1 is "stable"+3 months,
- SR2 is "stable"+6 months,
- SR3 is "stable"+9 months.
Milestones allow to commit on delivering most priority features and bug fixes first, and move towards stabilization when reaching Release Candidates.
Release calendar
0.8 | 0.9 | 0.10 | 1.0 | |
---|---|---|---|---|
M1 | 05-Jul-2013 | 23-Aug-13 | 21-Feb-14 | |
M2 | *skipped* | 4-Oct-13 | 4-Apr-14 | |
RC1 | 02-Aug-2013 | 15-Nov-13 | 6-May-14 | |
final | 11-Feb-13 | 09-Aug-2013 | 6-Dec-13 | 6-Jun-14 |
Maintenance releases | ||||
SR1 | 15-Apr-13 | 30-Aug-13 | TBD | TBD |
SR2 | 10-Jun-13 | 29-Nov-13 | TBD | TBD |
SR3 | 28-Feb-14 | TBD | TBD |