Difference between revisions of "Equinox/p2/Helios/Plan"

< Equinox‎ | p2
(M4 - December 12th, 2008)
(Current Milestone Plan: M3 - October 31, 2008)
Line 12: Line 12:
 
* MD5 processing step to verify download integrity [Pascal]
 
* MD5 processing step to verify download integrity [Pascal]
 
* Identify all Eclipse SDK dependencies on Update Manager and determine work required to remove Update Manager dependency ('''Note: cross-project impact''')
 
* Identify all Eclipse SDK dependencies on Update Manager and determine work required to remove Update Manager dependency ('''Note: cross-project impact''')
 +
* Map out metadata authoring and development work flow ('''Note: impact on PDE tooling work''')
  
 
== Future Plans ==
 
== Future Plans ==

Revision as of 15:57, 10 September 2008

This page lays out milestone plans for the development of Equinox p2 in the Eclipse Galileo release (aka the Eclipse Platform version 3.5). For a high level feature plan, see Equinox/p2/Galileo/Features.


Current Milestone Plan: M3 - October 31, 2008

  • Convert from using URL to URI where possible [John]
  • Refactor repository managers to remove code duplication [John]
  • Revise Touchpoint action contribution model [Simon]
  • Integration of publisher with PDE build [Andrew N]
    • Rewrite generator app and Ant tasks to invoke publisher
  • Investigate use of Apache HTTP client [Scott]
  • MD5 processing step to verify download integrity [Pascal]
  • Identify all Eclipse SDK dependencies on Update Manager and determine work required to remove Update Manager dependency (Note: cross-project impact)
  • Map out metadata authoring and development work flow (Note: impact on PDE tooling work)

Future Plans

M4 - December 12th, 2008

  • Complete integration of publisher with PDE build [Andrew N]
  • Repository association feature work [John]

M5 - January 30th, 2009 - Major Feature Freeze

M6 - March 12th, 2009 - API Freeze

  • Polish API javadoc, package.html doc

M7 - May 1st, 2009 - Development Complete

Previous Plans

M1 - August 8th, 2008

  • Decompression
  • Bug triage, community assistance
  • Fixing critical defects and performance problems

M2 - September 19th, 2008

  • Planning
  • Focus on 3.4.1 defects
  • Port 3.4.1 fixes to 3.5 stream