(New page: == EclipseLink Ramp Down for Galileo == This page outlines the ramp down plan for EclipseLink release for Galileo. For reference, see Galileo Simultaneous Release, in particular the...)
 
(Ramp Down Details)
 
(4 intermediate revisions by the same user not shown)
Line 1: Line 1:
== EclipseLink Ramp Down for Galileo ==  
+
== ''DRAFT'' EclipseLink Ramp Down for Galileo ==  
  
 
This page outlines the ramp down plan for EclipseLink release for Galileo.
 
This page outlines the ramp down plan for EclipseLink release for Galileo.
  
 
For reference, see [[Galileo Simultaneous Release]],
 
For reference, see [[Galileo Simultaneous Release]],
in particular the [[Galileo Simultaneous Release#Milestones_and_Release_Candidates | Milestones and Release Candidates]].
+
in particular the [[Galileo Simultaneous Release#Milestones_and_Release_Candidates | Milestones and Release Candidates]].
  
 
== Ramp Down Details ==
 
== Ramp Down Details ==
 
Milestone builds for EclipseLink are being tracked here: [http://wiki.eclipse.org/EclipseLink/Release/1.1.1 EclipseLink 1.1.1].
 
Milestone builds for EclipseLink are being tracked here: [http://wiki.eclipse.org/EclipseLink/Release/1.1.1 EclipseLink 1.1.1].
 +
 +
* If a subsequent re-build is required, it will be only for showstoppers.
 +
** No later than May 14
 +
* Final RC build April 30th
 +
* M2  Apr 18, 2009
 +
* M1  Apr 07, 2009
 +
 +
1.1.2 - This release will be used for Galileo, and will be 1.1.1 plus the Release train requirements outlined below.
  
 
There is no plan to do a respin after April 30th, unless required for show stopper, or last minute build changes required to get into Galileo.  Post April 30th, EclipseLink 1.1.1 is locked and in a QA phase.
 
There is no plan to do a respin after April 30th, unless required for show stopper, or last minute build changes required to get into Galileo.  Post April 30th, EclipseLink 1.1.1 is locked and in a QA phase.
  
 
== Galileo Release Train ==
 
== Galileo Release Train ==
The [[Galileo Simultaneous Release#Milestones_and_Release_Candidates | table on this page]] tracks all the bugs that need to be closed by the Galileo timeframe.   
+
The [http://www.eclipse.org/projects/galileo_status.php table on this page] tracks all the bugs that need to be closed by the Galileo timeframe.   
  
 
Status on the open bugs as of May 5 2009:
 
Status on the open bugs as of May 5 2009:
Line 18: Line 26:
 
* 263363 - Signing of Jars.  Underway - Target - May 8th, ready for RC1.
 
* 263363 - Signing of Jars.  Underway - Target - May 8th, ready for RC1.
 
* 263368 - New and Noteworthy - Waiting on M7, Target May 8th, ready for RC1.
 
* 263368 - New and Noteworthy - Waiting on M7, Target May 8th, ready for RC1.
* 263377 - Babel PTT - The feasibility of doing this is being investigated.  EclipseLink is translatable, as it has been being translated for many years.
 
  
 
== Identifying Showstoppers ==
 
== Identifying Showstoppers ==
 
Bugs discovered in 1.1.1 are reviewed regularly, and can be voted on by commtters for inclusion in a potential respin.
 
Bugs discovered in 1.1.1 are reviewed regularly, and can be voted on by commtters for inclusion in a potential respin.

Latest revision as of 11:43, 12 May 2009

DRAFT EclipseLink Ramp Down for Galileo

This page outlines the ramp down plan for EclipseLink release for Galileo.

For reference, see Galileo Simultaneous Release, in particular the Milestones and Release Candidates.

Ramp Down Details

Milestone builds for EclipseLink are being tracked here: EclipseLink 1.1.1.

  • If a subsequent re-build is required, it will be only for showstoppers.
    • No later than May 14
  • Final RC build April 30th
  • M2 Apr 18, 2009
  • M1 Apr 07, 2009

1.1.2 - This release will be used for Galileo, and will be 1.1.1 plus the Release train requirements outlined below.

There is no plan to do a respin after April 30th, unless required for show stopper, or last minute build changes required to get into Galileo. Post April 30th, EclipseLink 1.1.1 is locked and in a QA phase.

Galileo Release Train

The table on this page tracks all the bugs that need to be closed by the Galileo timeframe.

Status on the open bugs as of May 5 2009:

  • 263366 - Orbit. EclipseLink has uploaded the required jars to Orbit - waiting on the next Orbit milestone to make required build changes.
  • 263363 - Signing of Jars. Underway - Target - May 8th, ready for RC1.
  • 263368 - New and Noteworthy - Waiting on M7, Target May 8th, ready for RC1.

Identifying Showstoppers

Bugs discovered in 1.1.1 are reviewed regularly, and can be voted on by commtters for inclusion in a potential respin.