Difference between revisions of "EDT:0.8.1 Planning"

(New page: == Schedule for EDT 0.8.0 == 0.8.1 will be the next incubator release for EDT. The proposed release date is the end of July 2012. We will be developing in short milestones, to support ou...)
 
Line 1: Line 1:
== Schedule for EDT 0.8.0 ==
+
== Schedule for EDT 0.8.1 ==
  
 
0.8.1 will be the next incubator release for EDT. The proposed release date is the end of July 2012. We will be developing in short milestones, to support our Agile development process.  
 
0.8.1 will be the next incubator release for EDT. The proposed release date is the end of July 2012. We will be developing in short milestones, to support our Agile development process.  
Line 15: Line 15:
 
*Release Candidate  (July 16)  
 
*Release Candidate  (July 16)  
 
*Golden Master (July 20)  
 
*Golden Master (July 20)  
*0.8.0 Release (July 27)
+
*0.8.1 Release (July 27)
== Proposed Content for EDT 0.8.0<br>  ==
+
== Proposed Content for EDT 0.8.1<br>  ==
  
  
  
 
[[Category:EDT]]
 
[[Category:EDT]]

Revision as of 10:26, 19 April 2012

Schedule for EDT 0.8.1

0.8.1 will be the next incubator release for EDT. The proposed release date is the end of July 2012. We will be developing in short milestones, to support our Agile development process.

  • Milestone 1
    • Devt (Apr 23 - May 4)
    • FVT (May 7 - May 11)
  • Milestone 2
    • Devt (May 14 - May 25)
    • FVT (May 28 - June 1)
  • Milestone 3
    • Devt (June 4 - June 15)
    • FVT (June 18 - June 22)
  • SVT (June 25 - July 13)
  • Release Candidate  (July 16)
  • Golden Master (July 20)
  • 0.8.1 Release (July 27)

Proposed Content for EDT 0.8.1