* Milestone 1 (5/27/2011) - focus on Innovate 2011
+
* Milestone 1 (5/27/2011)
 
** [[EDT:0.7.0 Planning:Iteration 4]]  (4/4-4/15)
 
** [[EDT:0.7.0 Planning:Iteration 4]]  (4/4-4/15)
 
** [[EDT:0.7.0 Planning:Iteration 5]]  (4/18-4/29)
 
** [[EDT:0.7.0 Planning:Iteration 5]]  (4/18-4/29)
 
** [[EDT:0.7.0 Planning:Iteration 6]]  (5/2-5/13)
 
** [[EDT:0.7.0 Planning:Iteration 6]]  (5/2-5/13)
 
** [[EDT:0.7.0 Planning:Iteration 7]]  (5/16-5/27)
 
** [[EDT:0.7.0 Planning:Iteration 7]]  (5/16-5/27)
* Milestone 2 (7/22/2011) - focus on expanding major features (extensibility, IDE, debug, generators, runtimes, services, RUI), and adding data base support
+
* Milestone 2 (8/5/2011)  
 
** [[EDT:0.7.0 Planning:Iteration 8]]  (5/31-6/17)
 
** [[EDT:0.7.0 Planning:Iteration 8]]  (5/31-6/17)
 
** [[EDT:0.7.0 Planning:Iteration 9]]  (6/20-7/8)
 
** [[EDT:0.7.0 Planning:Iteration 9]]  (6/20-7/8)
** [[EDT:0.7.0 Planning:Iteration 10]]  (7/11-7/22)
+
** [[EDT:0.7.0 Planning:Iteration 10]]  (7/11-7/22)  
* Milestone 3 (9/2/2011) - focus on fit and finish of all components
+
** [[EDT:0.7.0 Planning:Iteration 11]]  (7/25-8/5)
** [[EDT:0.7.0 Planning:Iteration 11]]  (7/25-8/5)
+
* Milestone 3 (9/16/2011)  
 
** [[EDT:0.7.0 Planning:Iteration 12]]  (8/8-8/19)
 
** [[EDT:0.7.0 Planning:Iteration 12]]  (8/8-8/19)
 
** [[EDT:0.7.0 Planning:Iteration 13]]  (8/22-9/2)
 
** [[EDT:0.7.0 Planning:Iteration 13]]  (8/22-9/2)
* Release Candidate 1 (9/9/2011)
+
** [[EDT:0/7/0 Planning:Iteration 14}}  (9/5-9/16) - final cleanup
* Final Build (9/16/2011)
+
* Release Candidate 1 (9/23/2011)
 +
* 0.7.0 Availability (9/30/2011)
  
 