Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "ECF Conference Call 7.17.2008"

('''COMMITTER ACTION''')
('''COMMITTER ACTION''')
 
(One intermediate revision by the same user not shown)
Line 13: Line 13:
 
=='''COMMITTER ACTION'''==
 
=='''COMMITTER ACTION'''==
  
*Choose 2.1 Release Date (following are proposed):
+
*The following are possible ECF 2.1 Release Dates:
 
**Monday, September 8, 2008 (before Sept 24 2.0.1 Ganymede service release)
 
**Monday, September 8, 2008 (before Sept 24 2.0.1 Ganymede service release)
 
**Monday, September 29, 2008
 
**Monday, September 29, 2008
  
*ECF 2.1 Release Planning
+
'''Committer Action''':  Please weigh in on the ecf-dev mailing list about your availability for working on 2.1-targeted release content.  Will we collectively have enough done to justify a 2.1 release by Sept 8?
**See [[ECF/Plan for 2.1]]
+
 
*ECF 3.0 Release Planning
+
*ECF 2.1 Release Planning - See [[ECF/Plan for 2.1]]
**See [[ECF/Plan for 3.0]]
+
 
 +
'''Committer Action''':  Please review, comment, and amend [[ECF/Plan for 2.1]]
 +
 
 +
*ECF 3.0 Release Planning  
 +
 
 +
'''Committer Action''':  Please review, comment, and amend [[ECF/Plan for 3.0]]

Latest revision as of 15:10, 17 July 2008

Attendees

  • Scott Lewis, Ted Kubaska, Mustafa Isik, Remy Suen

Agenda

  • Decide on date for 2.1 Release

ECF Release Schedule

  • 2.0.1 - Ganymede SR Sept 24
  • 2.1
    • Notes: Minor Release (X.1) requires review, Need to also do Runtime project Move review

COMMITTER ACTION

  • The following are possible ECF 2.1 Release Dates:
    • Monday, September 8, 2008 (before Sept 24 2.0.1 Ganymede service release)
    • Monday, September 29, 2008

Committer Action: Please weigh in on the ecf-dev mailing list about your availability for working on 2.1-targeted release content. Will we collectively have enough done to justify a 2.1 release by Sept 8?

Committer Action: Please review, comment, and amend ECF/Plan for 2.1

  • ECF 3.0 Release Planning

Committer Action: Please review, comment, and amend ECF/Plan for 3.0