DTP PMC and Project Lead Meeting Minutes: June 2, 2008
Revision as of 12:43, 2 June 2008 by Brianf.sybase.com (Talk | contribs) (New page: ← Back to DTP PMC and Project Lead Meeting page ==Attendees== *Brian Fitzpatrick *Sheila Sholars *Larry Dunnell *Brian Payton *John Graham *Der ...)
← Back to DTP PMC and Project Lead Meeting page
Contents
Attendees
- Brian Fitzpatrick
- Sheila Sholars
- Larry Dunnell
- Brian Payton
- John Graham
- Der Ping Chou
- Emily Kapner
- Hung Hsi
- Linda Chan
Regrets
Agenda
- Beginning testing phase for RC3 with 6/2 1.6 RC3 build candidate on 3.3.2 and 3.4
- Doshiro status - Hung, please provide CVS/SVN package information to finish the committer process
- Hung, please have Max look into bug 233453 (https://bugs.eclipse.org/bugs/show_bug.cgi?id=233453) - this is a critical fix we should try and squeeze into RC3 or get into RC4
- Working on getting the Connectivity/SQL Dev Tools help in as part of the normal DTP build, should be done by RC4
- We are up to 23 bugs with no target milestone set that need to be dispositioned. Please keep at this list daily if at all possible.
- Sub-project status (from team leads)
- Open discussion