==Action Items==
 
==Action Items==
 
* Add 1.6.1 RC1/RC2/RC3 target milestones
 
* Add 1.6.1 RC1/RC2/RC3 target milestones
 +
* Ask Xiaoying to preserve tags for the final M1 build, tell the committers not do deliver any fixes to M1 (branch is no longer active)
  
 
==Tabled for Later Discussion==
 
==Tabled for Later Discussion==
  
 
[[Category:Data Tools Platform]]
 
[[Category:Data Tools Platform]]

Revision as of 14:26, 19 August 2008

Back to DTP PMC Meeting Page

Attendees

  • Brian Fitzpatrick
  • Linda Chan
  • John Graham
  • Sheila Sholars

Regrets

Agenda

  • 1.6.1 Rampdown policy (this is a modification to http://wiki.eclipse.org/DTP_1.6.1_Schedule_and_Rampdown_Policy)
    • M2 is August 25, 2008
    • Ganymede SR1 release train as a +1 project. Those dates are [[here].
      • September 2, 2008 - RC1
      • September 9, 2008 - RC2
      • September 16, 2008 - RC3 (Final Release, available September 24, 2008)
  • Proposed policy:
    • Open for fixes until afternoon of August 25, 2008 (SH time)
    • Team lead approval needed for any fixes the week of August 25 - August 28
    • August 29 (SH time) build will be the RC1 integration build. Test on August 29 & September 1, rebuild if issues arise
    • Week of September 1 - September 4, PMC approval required (reasons, implications, testing, patch)
    • September 5 (SH time) build will be the RC2 integration build. Test on September 5 & September 8, rebuild if issues arise
    • Just testing after that until September 16
  • Galileo planning
    • DTP Galileo Planning Draft
    • Need input from each PMC member's company to contribute to the Galileo effort
      • What priorities do you have? Where do you plan on contributing resources?
    • Actuate/ODA initial list of high-level projects (thanks Linda!)
      • Define filtering spec for support by any ODA data source queries
      • Integrate ODA framework with SQL Query Model to provide dynamic query conditions at runtime
      • Support for Multi-dimensional Result Sets
      • Enhance ODA Framework and API to support advanced features requested by the community. For example, dynamic creation of connection profile instance, support ODA data source-defined object type.
  • Open discussion

Minutes

  • Some concerns about the rampdown -- discussed the following
    • Adjust approvals by a week
      • Component Lead Approval (M2 to RC1)
      • Team Lead Approval (RC1 to RC2)
      • PMC Approval (RC2 to RC3) - PMC approval = ALL approve it (4/4)
      • Builds are request only (not nightly) during RC2 to RC3 period

Action Items

  • Add 1.6.1 RC1/RC2/RC3 target milestones
  • Ask Xiaoying to preserve tags for the final M1 build, tell the committers not do deliver any fixes to M1 (branch is no longer active)

Tabled for Later Discussion