Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "DTP Ganymede Rampdown Policy"

Line 19: Line 19:
 
==Rampdown Cycles==
 
==Rampdown Cycles==
  
===DTP 1.6RC0(M7): May 5 (M)===
+
===DTP 1.6RC0(M7): May 5 (Monday)===
 
*From Monday, 5/5, through Wednesday, 5/7: Testing Pass
 
*From Monday, 5/5, through Wednesday, 5/7: Testing Pass
 
*From Thursday, 5/8, through Friday, 5/16: Testing & Fix Pass
 
*From Thursday, 5/8, through Friday, 5/16: Testing & Fix Pass
  
===DTP 1.6RC1: May 19 (M)===
+
===DTP 1.6RC1: May 19 (Monday)===
 
*From Monday, 5/19, through Tuesday, 5/20: Testing Pass
 
*From Monday, 5/19, through Tuesday, 5/20: Testing Pass
 
*From Wednesday, 5/21, through Friday, 5/23: Testing & Fix Pass
 
*From Wednesday, 5/21, through Friday, 5/23: Testing & Fix Pass
  
===DTP 1.6RC2: May 26 (M)===
+
===DTP 1.6RC2: May 26 (Monday)===
 
*From Monday, 5/26, through Wednesday, 5/28: Testing Pass
 
*From Monday, 5/26, through Wednesday, 5/28: Testing Pass
 
*From Thursday, 5/29, through Friday, 5/30: Testing & Fix Pass
 
*From Thursday, 5/29, through Friday, 5/30: Testing & Fix Pass
  
===DTP 1.6RC3: June 2 (M)===
+
===DTP 1.6RC3: June 2 (Monday)===
 
*From Monday, 6/2, through Wednesday, 6/4: Testing Pass
 
*From Monday, 6/2, through Wednesday, 6/4: Testing Pass
 
*From Thursday, 6/5, through Friday, 6/6: Testing & Fix Pass
 
*From Thursday, 6/5, through Friday, 6/6: Testing & Fix Pass
  
===DTP 1.6RC4: June 9 (M)===
+
===DTP 1.6RC4: June 9 (Monday)===
 
*From Monday, 6/9, through Ganymede release: Testing Pass
 
*From Monday, 6/9, through Ganymede release: Testing Pass
  

Revision as of 13:50, 26 February 2008

Back to DTP Main Page

Status

[2/26/08]: This document is a draft and has not been approved by the DTP PMC.

Purpose

This document defines a set of rampdown cycles for DTP 1.6. The goal is to ensure that DTP stability and completeness converges on the 1.6 release dates, while allowing mechanisms for changes as necessary. Since this document is about the rampdown, only cycles post DTP 1.6RC0 will be detailed below.

Rampdown Cycle Phases

Testing Pass

A period of testing during which no changes are made to the DTP code line, unless approved by the PMC. Nightly builds will not be produced during this pass. In general, we ask everyone in the DTP community to test the target build as thoroughly as possible.

Testing & Fix Pass

A Testing Pass including bug fixes based on the approval policies described below. Nightly build will be produced during this period as necessary to make bug fixes available to the DTP community.

Rampdown Cycles

DTP 1.6RC0(M7): May 5 (Monday)

  • From Monday, 5/5, through Wednesday, 5/7: Testing Pass
  • From Thursday, 5/8, through Friday, 5/16: Testing & Fix Pass

DTP 1.6RC1: May 19 (Monday)

  • From Monday, 5/19, through Tuesday, 5/20: Testing Pass
  • From Wednesday, 5/21, through Friday, 5/23: Testing & Fix Pass

DTP 1.6RC2: May 26 (Monday)

  • From Monday, 5/26, through Wednesday, 5/28: Testing Pass
  • From Thursday, 5/29, through Friday, 5/30: Testing & Fix Pass

DTP 1.6RC3: June 2 (Monday)

  • From Monday, 6/2, through Wednesday, 6/4: Testing Pass
  • From Thursday, 6/5, through Friday, 6/6: Testing & Fix Pass

DTP 1.6RC4: June 9 (Monday)

  • From Monday, 6/9, through Ganymede release: Testing Pass

Additional RC Builds

Additional RC builds will be scheduled as necessary.