Status

  • 9/21/10 - Draft started, to be reviewed by PMC

Purpose

This document defines a schedule and set of ramp-down policies for DTP 1.9 (Indigo). The goal is to ensure that DTP stability and completeness converges on the 1.9 release dates, while allowing mechanisms for changes as necessary.

Schedule

DTP is on the Indigo release train as a +1 project. These dates are based on the [Indigo Simultaneous Release Plan]

  • 1.9M1 - August 16, 2010 (publicly available 8/20/10)
  • 1.9M2 - September 27, 2010 (publicly available 10/1/10)
  • 1.9M3 - November 8, 2010 (publicly available 11/12/10)
  • 1.9M4 - December 13, 2010 (publicly available 12/17/10)
  • 1.9M5 - February 7, 2011 (publicly available 2/11/11)
  • 1.9M6 - March 11, 2011 (publicly available 3/18/11)
  • 1.9M7 - May 2, 2011 (publicly available 5/6/11)
  • 1.9RC1 - May 16, 2011 (publicly available 5/20/11)
  • 1.9RC2 - May 23, 2011 (publicly available 5/28/11)
  • 1.9RC3 - May 30, 2011 (publicly available 6/3/11)
  • 1.9RC4 - June 6, 2011 (publicly available 6/10/11)
  • 1.9 Release - June 22, 2011