Cosmos Release Plan

Revision as of 12:39, 3 December 2008 by Ruthdaly.ca.ibm.com (Talk | contribs) (Release Milestones)

COSMOS Wiki > COSMOS Work Items

COSMOS 1.1 Release Plan

Overview

Please send comments about this plan to the cosmos-mgmt@eclipse.org project management mailing list.


This document lays out the feature and API set for the COSMOS releases.

This plan describes the deliverables, milestones, and plan items for the COSMOS project. Each plan item covers a feature or API that is to be added to COSMOS, or some aspect of COSMOS that is to be improved. Each plan item has its own entry in the COSMOS bugzilla database, with a title and a concise summary (usually a single paragraph) that explains the work item at a suitably high level so that everyone can readily understand the work item.


Fixing bugs, improving test coverage, documentation, examples, performance tuning, usability, etc. are considered routine ongoing maintenance activities and are not included in this plan unless they would also involve a significant change to the API or feature set, or involve a significant amount of work. The intent of the plan is to account for all interesting feature work.

Release Deliverables

The following release deliverables are provided:

  • Runtime
  • Tooling
  • Source
  • Examples
  • Component Tests
  • Data Collection Implementation
  • Data Visualization Implementation
  • Resource Modeling Implementation
  • Management Enablement Implementation
  • CMDBf Implementation

Release Milestones

This COSMOS 1.1 is targeted for general availability on 26-June-2009. All deliverables will be available for download as soon as the release has been tested and validated in the target configurations. There is an allocation of resource to defect removal in all iterations. The first Iterations 1-2 will contain the bulk of the enhancement work, with Iteration 3 stabilizing the milestone driver, with Iteration 4 finishing the enhancement work, and Iteration 5 will mainly be used to stabilize and shut down the release.


MilestoneDuration Planned Start Date Planned End Date Actual Start Date Actual End Date Description Comments
Iteration 18 weeks Nov-17-2009 Jan-09-2009     Enhancements  
   i1 Development 5 weeks Nov-17-2009 Dec-19-2009     Development & bug fixes  
i1 Testing 3 weeks Dec-22-2009 Jan-09-2009     Validation Testing  
Iteration 26 weeks Jan-12-2009 Feb-20-2009     Enhancements  
   i2 Development 4 weeks Jan-12-2009 Feb-06-2009     Development & bug fixes  
i2 Testing 2 weeks Feb-09-2009 Feb-20-2009     Validation Testing  
Iteration 36 weeks Feb-23-3009 Apr-03-2009     Stabilize  
   i3 Development 4 weeks Feb-23-2009 Mar-20-2009     Development & bug fixes  
i3 Testing 2 weeks Mar-23-2009 Apr-03-2009     Validation Testing  
Milestone driver1 day Apr-03-2009 Apr-03-2009     Available for POCs  
Iteration 46 weeks Apr-06-2009 May-15-2009     Enhancements  
   i4 Development 4 weeks Apr-06-2009 May-01-2009     Development & bug fixes  
i4 Testing 2 weeks May-04-2009 May-15-2009     Validation Testing  
Iteration 56 weeks May-18-2009 June-26-2009     Stabilize  
   i5 Development 4 weeks May-18-2009 June-12-2009     Development & bug fixes  
i5 Testing 2 weeks June-15-2009 June-26-2009     Validation Testing  
COSMOS 1.1 availability1 day June-26-2009 June-26-2009     GA Release  

Major deliverables

  • SML bug fixes
  • reconciliation taxonomy
  • finish the SDD tooling for the BTG
  • have our SDD runtime driver for conformance level 1
  • stabilize CMDBf support
  • move SML out of research
  • move SDD out of research

Features

Plan items targeted for this release represent the addition of new features or areas where existing features will be significantly reworked or enhanced. Plan items are allocated to the projects indicated above.

Milestone 1 Objectives (i1 - i3)

GA Objectives (i4 - i5)