Difference between revisions of "COSMOS Project Plan"

Line 33: Line 33:
  
 
* Iteration 1;  Code Freeze 2/28.  Iteration 1 complete March 05.  (demo)
 
* Iteration 1;  Code Freeze 2/28.  Iteration 1 complete March 05.  (demo)
** http://wiki.eclipse.org/index.php/COSMOSWeeklyProjectPlanForMarch07
+
** http://wiki.eclipse.org/index.php/COSMOSWeeklyProjectPlan
 
* Iteration 2:  Complete iteration 2 by 4/16.  (need i2 plan)   
 
* Iteration 2:  Complete iteration 2 by 4/16.  (need i2 plan)   
 
* Iteration 3:  Complete iteration 3 by 5/28  (need i3 plan) to ship along with Europa.
 
* Iteration 3:  Complete iteration 3 by 5/28  (need i3 plan) to ship along with Europa.

Revision as of 16:59, 29 March 2007

COSMOS Project Home > COSMOS Wiki > COSMOS Documents >


COSMOS RELEASE SCHEDULE FOR 2007

Link to Europa Release: http://wiki.eclipse.org/index.php/Europa_Simultaneous_Release

Milestone/Task Planned Start Planned End Actual Start Actual End % Complete Comments
Iteration 1-3 definition 01/01/07 03/19/07 - - - on track
Iteration 1 demo development 01/01/07 02/23/07 - - - on track
Release 1 requirement priority 03/05/07 03/19/07 - - - on track
Release vote by community 03/05/07 03/23/07 - - - on track
Release 1 plan closure 03/20/07 03/30/07 - - - on track
Iteration 2 development and test 02/23/07 04/06/07 - - - at risk
Iteration 3 development and test 04/01/07 05/18/07 - - - -
Iteration 4 development and test 05/01/07 06/15/07 - - - -
Code Freeze 06/01/07 06/23/07 - - - -
Europa GA 06/29/07 06/29/07 - - - to ship alongside