COSMOS RELEASE SCHEDULE FOR 2007
+
h2. COSMOS RELEASE SCHEDULE FOR 2007
  
Iteration 1;  Code Freeze 2/28.  Iteration 1 complete March 05.  (demo)
+
* Iteration 1;  Code Freeze 2/28.  Iteration 1 complete March 05.  (demo)
Iteration 2:  Complete iteration 2 by 4/16.  (need i2 plan)   
+
* Iteration 2:  Complete iteration 2 by 4/16.  (need i2 plan)   
Iteration 3:  Complete iteration 3 by 5/28  (need i3 plan) to ship along with Europa.
+
* Iteration 3:  Complete iteration 3 by 5/28  (need i3 plan) to ship along with Europa.

Revision as of 15:02, 8 February 2007

h2. COSMOS RELEASE SCHEDULE FOR 2007

  • Iteration 1; Code Freeze 2/28. Iteration 1 complete March 05. (demo)
  • Iteration 2: Complete iteration 2 by 4/16. (need i2 plan)
  • Iteration 3: Complete iteration 3 by 5/28 (need i3 plan) to ship along with Europa.