Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "COSMOS Project Plan"
Line 1: | Line 1: | ||
− | COSMOS RELEASE SCHEDULE FOR 2007 | + | h2. COSMOS RELEASE SCHEDULE FOR 2007 |
− | Iteration 1; Code Freeze 2/28. Iteration 1 complete March 05. (demo) | + | * Iteration 1; Code Freeze 2/28. Iteration 1 complete March 05. (demo) |
− | Iteration 2: Complete iteration 2 by 4/16. (need i2 plan) | + | * Iteration 2: Complete iteration 2 by 4/16. (need i2 plan) |
− | Iteration 3: Complete iteration 3 by 5/28 (need i3 plan) to ship along with Europa. | + | * Iteration 3: Complete iteration 3 by 5/28 (need i3 plan) to ship along with Europa. |
Revision as of 15:02, 8 February 2007
h2. COSMOS RELEASE SCHEDULE FOR 2007
- Iteration 1; Code Freeze 2/28. Iteration 1 complete March 05. (demo)
- Iteration 2: Complete iteration 2 by 4/16. (need i2 plan)
- Iteration 3: Complete iteration 3 by 5/28 (need i3 plan) to ship along with Europa.