Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "COSMOS ME Minutes 24JUN08"

(Initial content)
 
(Removed an action item)
Line 57: Line 57:
 
# DOJO issues, remove from SDD for COSMOS?
 
# DOJO issues, remove from SDD for COSMOS?
 
# Jason to send Merri the URL for the Runtime Doc.
 
# Jason to send Merri the URL for the Runtime Doc.
# Jason to send out P2 meeting summary.
 
 
# Eric to push code for Change Analyzer.
 
# Eric to push code for Change Analyzer.
 
# Charlie to find out about Eclipse cross-project policies.
 
# Charlie to find out about Eclipse cross-project policies.

Revision as of 14:53, 30 June 2008

Logistics

  • Date: 24JUN08
  • Time: 11AM EST
  • Attendees: Charlie Halloran, Mark McCraw, Merri Jensen, Jeff Hamm, Robert DeMason, Jason Losh, Eric Rose, Chris Mildebrant, David Whiteman

Agenda

  1. i11 status updates
  2. Follow-up on action items
    • Jason to commit SAS zip extractor code, Mark to change packages to align with COSMOS requirements.
      • Changes have been made, ready to commit
    • Continue work on SDD for COSMOS
      • Dependent on DOJO situation (DOJO currently referenced in the draft SDD) - update ME team on DOJO situation
    • Jason to start documenting the Runtime similar to doc Chris has created for SDD Tooling (need URL).
      • Done for phase 1 - now alignment with P2
    • Eric to enter any additional Tooling ERs for i12?

Time permitting … alignment/integration topics

  1. P2/SDD runtime alignment
  2. SML/CML/SDD/OVF alignment
    • Ongoing
  3. CMDBf integration
    • Ongoing

Minutes

  1. i11 status update: http://wiki.eclipse.org/COSMOS/COSMOS_i11_candidate_No3
    • ERs still need status updates: 220639 - David - on track complete, 220594 - defer to i12, 230282 - move to i12.
  2. i12 closes the first week of August
    • Probably won't have SDD runtime ready, but will still need to list ERs that we will deliver for i12.
    • Ping Jason if you update the ME items in i12.
    • BTG going in for i13.
    • i12 is supposed to be more of a stability release, so aren't pushing many big development changes, but SDD is understandably an exception.
  3. Action Items:
    • Mark delivered refactored zip extractor code with unit tests w/ TPTP, Jason to push later in the week.
    • SDD for COSMOS, done for the most part, but references DOJO - there is an issue with DOJO and COSMOS related to Eclipse Legal issue, they have a problem with redistribution and its use even as a pre-req. Trying to lean on Eclipse legal to get this worked out.
    • TAKE-AWAY -- be very careful about third party components/source especially those of a "dubious pedigree", where possible use components that have already been approved in ipzilla. -- Cannot push code with third party source without having entered an ipzilla. -- There is also considerations for which company checks in the code as well.
    • Doc'ing runtime is done, ER marked fixed.
    • Alignment with P2 - Jeff started deep diving into code, Charlie to post doc from earlier meeting with concept mappings between P2 and SDD. Jason and Jeff decided to mind meld (which seems a little sketchy to me ;-)
  4. Time Permitting Items:
    • SML - Julia on the hook to discuss SDD alignment with SML in a couple of weeks.
    • P2
      • Mark had a question that I didn't quite get all of "Should we be looking at P2 for code that can be reused or to expand on the ?????" Jason's answer was to do both.
      • Jason still needs to check on cross-project rules and gotchas.
      • Basically, don't look at P2 with eye to beat it into submission but also don't look at it and say this is great but we're going to do it this way, we need to strike a balance between these two extremes with regard to P2.

Action Items

  1. Jason to commit SAS zip extractor code.
  2. DOJO issues, remove from SDD for COSMOS?
  3. Jason to send Merri the URL for the Runtime Doc.
  4. Eric to push code for Change Analyzer.
  5. Charlie to find out about Eclipse cross-project policies.
  6. Additional ERs for i12 need to be entered or sent to Jason.
  7. Continue looking at P2 code and see what it does.
  8. Julia to talk about SDD alignment with SML in a couple of weeks.
  9. Charlie to post P2/SDD concept mappings doc to wiki.

Back to the top