COSMOS Document Schedule
Revision as of 23:32, 30 January 2008 by Vasconi.us.ibm.com (Talk | contribs) (→COSMOS User's Guide)
COSMOS Wiki > COSMOS Document Plan
Contents
Documents
There will be two documents:
- COSMOS User's Guide
- COSMOS Developer's Guide
Availablility
- Documents available two weeks before GA
Milestones
The development of a document consists the following chronological milestones.
- First draft
- Review
- Second draft
- Review
- Final version distributed to reviewers
- Approval
- Create PDF and online helps
- Test online helps
COSMOS Document Schedule for GA
COSMOS User's Guide
Activity | Duration | Projected Date
|
---|---|---|
Development input | n/a | 03/12/08 |
- | - | -
|
First draft | _ | 04/09/08 |
First review | 5 days | o4/16/08 |
Second draft | _ | 05/21/08 |
Final review | 5 days | 05/28/08 |
Approval | _ | 06/04/08 |
HTML Helps version | _ | 06/09/08
|
COSMOS Development Guide
Activity | Duration | Projected Date
|
---|---|---|
First draft | n/a | 03/12/08 |
First review | 5 days | 03/19/08 |
Second draft | _ | 04/09/08 |
Second review | 5 days | o4/16/08 |
Final edited draft | _ | 05/21/08 |
Approval version | n/a | 06/02/08 |
HTML Helps version | _ | 06/04/08
|