Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

COSMOS Document Schedule

Revision as of 23:32, 30 January 2008 by Vasconi.us.ibm.com (Talk | contribs) (COSMOS User's Guide)

COSMOS Wiki > COSMOS Document Plan


Documents

There will be two documents:

  • COSMOS User's Guide
  • COSMOS Developer's Guide

Availablility

  • Documents available two weeks before GA

Milestones

The development of a document consists the following chronological milestones.

  1. First draft
  2. Review
  3. Second draft
  4. Review
  5. Final version distributed to reviewers
  6. Approval
  7. Create PDF and online helps
  8. Test online helps

COSMOS Document Schedule for GA

COSMOS User's Guide

Activity Duration Projected Date


Development input n/a 03/12/08
- - -


First draft _ 04/09/08
First review 5 days o4/16/08
Second draft _ 05/21/08
Final review 5 days 05/28/08
Approval _ 06/04/08
HTML Helps version _ 06/09/08


COSMOS Development Guide

Activity Duration Projected Date


First draft n/a 03/12/08
First review 5 days 03/19/08
Second draft _ 04/09/08
Second review 5 days o4/16/08
Final edited draft _ 05/21/08
Approval version n/a 06/02/08
HTML Helps version _ 06/04/08


Back to the top