COSMOS Document Schedule

Revision as of 22:45, 30 January 2008 by Vasconi.us.ibm.com (Talk | contribs) (COSMOS Document Schedule for GA)

COSMOS Wiki > COSMOS Document Plan


Documents

There will be two documents:

  • COSMOS User's Guide
  • COSMOS Developer's Guide

Availablility

  • Documents available two weeks before GA

Milestones

The development of a document consists the following chronological milestones.

  1. First draft
  2. Review
  3. Second draft
  4. Review
  5. Final version distributed to reviewers
  6. Approval
  7. Create PDF and online helps
  8. Test online helps

COSMOS Document Schedule for GA

Activity Duration Projected Date


First draft n/a 03/12/08
First review 5 days 03/19/08
Second draft _ 04/09/08
Second review 5 days o4/16/08
Final edited draft _ 05/21/08
Approval version n/a 06/02/08
HTML Helps version 5 days 06/04/08