Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "COSMOS Document Schedule"

(COSMOS Document Schedule for GA)
(COSMOS Document Schedule for GA)
Line 22: Line 22:
 
# Test online helps
 
# Test online helps
 
   
 
   
=== COSMOS Document Schedule for GA ===
+
== COSMOS Document Schedule for GA ==
 
+
  
 +
=== COSMOS User's Guide ===
  
 
{| border="1"
 
{| border="1"
Line 63: Line 63:
 
| 05/21/08
 
| 05/21/08
  
 +
|-
 +
| Approval version
 +
| n/a
 +
| 06/02/08
 +
|-
 +
| HTML Helps version
 +
| 5 days
 +
| 06/04/08
 +
 +
 +
|}
 +
 +
 +
=== COSMOS Development Guide ===
 +
 +
{| border="1"
 +
 +
 +
|-
 +
 +
! Activity
 +
! Duration
 +
 +
! Projected Date
 +
 +
|-
 +
 +
| Content Complete
 +
| n/a
 +
| 03/12/08
 +
|-
 +
| -
 +
| -
 +
| -
 +
 +
 +
|-
 +
 +
| First draft
 +
| n/a
 +
| 04/09/08
 +
|-
 +
| First review
 +
| 5 days
 +
| 04/16/08
 +
 +
|-
 +
 +
| Second draft
 +
| _
 +
| 05/07/08
 +
|-
 +
| Final review
 +
| 5 days
 +
| o5/14/08
 +
 +
 
|-
 
|-
 
| Approval version
 
| Approval version

Revision as of 23:20, 30 January 2008

COSMOS Wiki > COSMOS Document Plan


Documents

There will be two documents:

  • COSMOS User's Guide
  • COSMOS Developer's Guide

Availablility

  • Documents available two weeks before GA

Milestones

The development of a document consists the following chronological milestones.

  1. First draft
  2. Review
  3. Second draft
  4. Review
  5. Final version distributed to reviewers
  6. Approval
  7. Create PDF and online helps
  8. Test online helps

COSMOS Document Schedule for GA

COSMOS User's Guide

Activity Duration Projected Date


First draft n/a 03/12/08
First review 5 days 03/19/08
Second draft _ 04/09/08
Second review 5 days o4/16/08
Final edited draft _ 05/21/08
Approval version n/a 06/02/08
HTML Helps version 5 days 06/04/08



COSMOS Development Guide

Activity Duration Projected Date
Content Complete n/a 03/12/08
- - -


First draft n/a 04/09/08
First review 5 days 04/16/08
Second draft _ 05/07/08
Final review 5 days o5/14/08


Approval version n/a 06/02/08
HTML Helps version 5 days 06/04/08