COSMOSWeeklyProjectPlan
Revision as of 20:32, 18 January 2007 by Cthomas.groundworkopensource.com (Talk | contribs)
Week by Week Plan to get to the March Demo
Data Reporting
This is an under-reviewed, placeholder plan for work from the Data Reporting Sub Project. Still needs review and input from Sheldon. Also note that the mockups, now linked from the COSMOSEclipseCon2007Demo, need wider review.
Date | Milestone | Dependencies | Who |
26-Jan-2007 | Topologies Report | Marius' work on getTopologies() Valentina's work on SML-IF for demo |
Sheldon |
2-Feb-2007 | Nodes Report, Properties Report | Marius' work on getNodeProperties(nodeId) | Sheldon |
9-Feb-2007 | Node Log Report | Ability to reuse TPTP's existing BIRT report for windows log data. Or Data Collection team's ability to import windows log data into RDBMS plus Marius' ability to provide a getLogData(node_id) or whatever the right API is. |
Sheldon |
16-Feb-2007 | Refactor APIs, beautify reports | none known | Sheldon |