Week by Week Plan to get to the March Demo
+
Week by Week Plan to get to the March Demo.
  
== Data Reporting ==
+
== Resource Modeling ==
This is the sub-project plan with milestones.
+
{{CTable|tableWidth=100%}}
 
+
Information reviewed with Sheldon and Marius ([[User:Cthomas.groundworkopensource.com|Cthomas.groundworkopensource.com]] 14:20, 1 February 2007 (EST))
+
+
{{CTable}}
+
 
| Date
 
| Date
 
| Milestone
 
| Milestone
Line 12: Line 8:
 
| Who
 
| Who
 
|-
 
|-
|2-Feb-2007
+
| 2-Feb-2007
|SMLIF editor
+
| SMLIF editor  
 
(The code will be fully functional by Feb 2)
 
(The code will be fully functional by Feb 2)
|None
+
| None
|Ali
+
| Ali
 
|-
 
|-
|2-Feb-2007
+
| 2-Feb-2007
|Import from SMLIF and export to SMLIF actions
+
| Import from SMLIF and export to SMLIF actions
 
(The code will be fully functional by Feb 2)
 
(The code will be fully functional by Feb 2)
|None
+
| None
|David
+
| David
 
|-
 
|-
|2-Feb-2007
+
| 2-Feb-2007
|SML and SMLIF documents
+
| SML and SMLIF documents
 
(the instances are already available in CVS; Ali to make any required changes)
 
(the instances are already available in CVS; Ali to make any required changes)
|None
+
| None
|Ali
+
| Ali
 +
|}
 +
== Data Reporting ==
 +
This is the sub-project plan with milestones.
 +
 
 +
Information reviewed with Sheldon and Marius ([[User:Cthomas.groundworkopensource.com|Cthomas.groundworkopensource.com]] 14:20, 1 February 2007 (EST))
 +
 +
{{CTable}}
 +
| Date
 +
| Milestone
 +
| Dependencies
 +
| Who
 
|-
 
|-
 
| 26-Jan-2007
 
| 26-Jan-2007

Revision as of 16:23, 6 February 2007

Week by Week Plan to get to the March Demo.

Resource Modeling

Date Milestone Dependencies Who
2-Feb-2007 SMLIF editor

(The code will be fully functional by Feb 2)

None Ali
2-Feb-2007 Import from SMLIF and export to SMLIF actions

(The code will be fully functional by Feb 2)

None David
2-Feb-2007 SML and SMLIF documents

(the instances are already available in CVS; Ali to make any required changes)

None Ali

Data Reporting

This is the sub-project plan with milestones.

Information reviewed with Sheldon and Marius (Cthomas.groundworkopensource.com 14:20, 1 February 2007 (EST))


Date Milestone Dependencies Who
26-Jan-2007 Topologies Report
  • Marius' work on getTopologies()
  • Valentina's work on SML-IF for demo ( Valentina : this work has been done by Ali )
  • Sheldon's review of this plan
Sheldon
2-Feb-2007 Nodes Report, Properties Report
  • Marius' work on getNodeProperties(nodeId)
Sheldon
9-Feb-2007 "top 10 report" of CBE data (https://bugs.eclipse.org/bugs/show_bug.cgi?id=172538)
  • Marius' API to provide a getLogData(node_id) or whatever the right API name is.
Sheldon
16-Feb-2007
  • API to provide a getStatisticalData(node_id) or whatever the right API name is.
Sheldon