Difference between revisions of "BIRT2.6 Rampdown Policy"

(Date)
Line 46: Line 46:
 
Tuesday June 8 until Tuesday June 15 (Helios Release): Testing Pass.<br/>   
 
Tuesday June 8 until Tuesday June 15 (Helios Release): Testing Pass.<br/>   
 
Additional RC Builds will be scheduled as necessary.<br/>
 
Additional RC Builds will be scheduled as necessary.<br/>
 +
 +
[[Category:BIRT]]

Revision as of 17:28, 13 May 2010

Purpose

This document describes a set of ramp down rules for the BIRT 2.6 Release. The Builds and Release decisions occurs on the dates listed for each Release Candidate.

Date

May 18 : BIRT 2.6 RC1

Through May 14, Testing and Fix pass.
Monday May 17 : BIRT 2.6 RC1 Candidate build.
Monday May 17 until Tuesday May 18: RC1 Candidate testing. Helios update site update.
Tuesday May 18 until Wednesday May 19: Candidate build repackage with WTP3.2 RC1 and vote for the candidate build.


May 25 : BIRT 2.6 RC2

Tuesday May 18 through May 23, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday May 24 : BIRT 2.6 RC2 Candidate build.
Monday May 24 until Tuesday May 25: RC2 Candidate testing. Helios update site update.
Tuesday May 25 until Wednesday May 26: Candidate build repackage with WTP3.2 RC2 and vote for the candidate build.


June 1 : BIRT 2.6 RC3

Tuesday May 25 through May 30, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday May 31: BIRT 2.6 RC3 Candidate build.
Monday May 31 until Tuesday June 1: RC3 Candidate testing. Helios update site update.
Tuesday Jun 1 until Wednesday Jun 2: Candidate build repackage with WTP3.2 RC3 and vote for the candidate build.


June 08: BIRT 2.6 RC4

Wednesday June 2 through June 6 Testing and Fix pass. All Bug fixes must be approved by the at least two project leads and BIRT PMC.
Monday June 7: BIRT 2.6 RC4 Candidate build.
Monday June 7 until Tuesday June 8: RC4 Candidate testing. Helios update site update.
Tuesday June 8 until Wednesday June 9: Candidate build repackage with WTP3.2 RC4 and vote for the candidate build.


Post BIRT 2.6 RC4 through Helios Release

Tuesday June 8 until Tuesday June 15 (Helios Release): Testing Pass.
Additional RC Builds will be scheduled as necessary.