BIRT2.3 Rampdown Policy
Purpose
This document describes a set of ramp down rules for the BIRT 2.3 Release. The Builds and Release decisions occurs on the dates listed for each Release Candidate
Date
May 6 : BIRT 2.3 RCO
Through May 4, Testing and Fix pass.
Monday May 5 : BIRT 2.3 RCO Candidate build
Monday May 5 until Tuesday May 6: RCO Candidate testing. Ganymede update site update.
Tuesday May 6 until Wednesday May 7: Candidate build repackage with WTP RC0 and vote for the candidate build.
May 20 : BIRT 2.3 RC1
Through May 18, Testing and Fix pass.
Monday May 19 : BIRT 2.3 RC1 Candidate build
Monday May 19 until Tuesday May 20: RC1 Candidate testing. Ganymede update site update.
Tuesday May 20 until Wednesday May 21: Candidate build repackage with WTP RC1 and vote for the candidate build.
May 27 : BIRT 2.3 RC2
Tuesday May 20 through May 25, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday May 26 : BIRT 2.3 RC1 Candidate build
Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update.
Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC3 and vote for the candidate build.
June 3 : BIRT 2.3 RC3
Tuesday May 27 through June 1, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday Jun 2: BIRT 2.3 RC3 Candidate build
Monday Jun 2 until Tuesday June 3: RC3 Candidate testing. Ganymede update site update.
Tuesday Jun 3 until Wednesday Jun 4: Candidate build repackage with WTP RC3 and vote for the candidate build.