Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

BIRT2.3 Rampdown Policy

Revision as of 01:17, 8 May 2008 by Xgu.actuate.com (Talk | contribs) (Date)

Purpose

This document describes a set of ramp down rules for the BIRT 2.3 Release. The Builds and Release decisions occurs on the dates listed for each Release Candidate

Date

May 6 : BIRT 2.3 RCO

Through May 4, Testing and Fix pass.
Monday May 5 : BIRT 2.3 RCO Candidate build
Monday May 5 until Tuesday May 6: RCO Candidate testing. Ganymede update site update.
Tuesday May 6 until Wednesday May 7: Candidate build repackage with WTP RC0 and vote for the candidate build.


May 20 : BIRT 2.3 RC1

Through May 18, Testing and Fix pass.
Monday May 19 : BIRT 2.3 RC1 Candidate build
Monday May 19 until Tuesday May 20: RC1 Candidate testing. Ganymede update site update.
Tuesday May 20 until Wednesday May 21: Candidate build repackage with WTP RC1 and vote for the candidate build.


May 27 : BIRT 2.3 RC2

Tuesday May 20 through May 25, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday May 26 : BIRT 2.3 RC1 Candidate build
Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update.
Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC3 and vote for the candidate build.


June 3 : BIRT 2.3 RC3

Tuesday May 27 through June 1, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday Jun 2: BIRT 2.3 RC3 Candidate build
Monday Jun 2 until Tuesday June 3: RC3 Candidate testing. Ganymede update site update.
Tuesday Jun 3 until Wednesday Jun 4: Candidate build repackage with WTP RC3 and vote for the candidate build.

Back to the top