Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
BIRT2.3 Rampdown Policy
Purpose
This document describes a set of ramp down rules for the BIRT 2.3 Release. The Builds and Release decisions occurs on the dates listed for each Release Candidate
Date
May 6 : BIRT 2.3 RCO
Through May 4, Testing and Fix pass.
Monday May 5 : BIRT 2.3 RCO Candidate build
Monday May 5 until Tuesday May 6: RCO Candidate testing. Ganymede update site update.
Tuesday May 6 until Wednesday May 7: Candidate build repackage with WTP RC0 and vote for the candidate build.
May 20 : BIRT 2.3 RC1
Through May 18, Testing and Fix pass.
Monday May 19 : BIRT 2.3 RC1 Candidate build
Monday May 19 until Tuesday May 20: RC1 Candidate testing. Ganymede update site update.
Tuesday May 20 until Wednesday May 21: Candidate build repackage with WTP RC1 and vote for the candidate build.
May 27 : BIRT 2.3 RC2
Through May 25, Testing and Fix pass.
Monday May 26 : BIRT 2.3 RC1 Candidate build
Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update.
Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC1 and vote for the candidate build.