Difference between revisions of "BIRT2.3 Rampdown Policy"

(Date)
(Date)
Line 27: Line 27:
 
Monday May 26 : BIRT 2.3 RC1 Candidate build <br/>  
 
Monday May 26 : BIRT 2.3 RC1 Candidate build <br/>  
 
Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update. <br/>
 
Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update. <br/>
Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC3 and vote for the candidate build. <br/>
+
Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC2 and vote for the candidate build. <br/>
  
  
Line 36: Line 36:
 
Monday Jun 2 until Tuesday June 3: RC3 Candidate testing. Ganymede update site update. <br/>
 
Monday Jun 2 until Tuesday June 3: RC3 Candidate testing. Ganymede update site update. <br/>
 
Tuesday Jun 3 until Wednesday Jun 4: Candidate build repackage with WTP RC3 and vote for the candidate build. <br/>
 
Tuesday Jun 3 until Wednesday Jun 4: Candidate build repackage with WTP RC3 and vote for the candidate build. <br/>
 +
 +
 +
'''June 10: BIRT 2.3 RC4'''
 +
 +
Thursday June 3 through Tuesday June 8 Testing and Fix pass. All Bug fixes must be approved by the at least two project leads and BIRT PMC <br/>
 +
Wednesday June 9: BIRT 2.3 RC4 Candidate build <br/>
 +
Wednesday June 9 until Thursday June 10: RC4 Candidate testing. Ganymede update site update. <br/>
 +
Tuesday Jun 10 until Wednesday Jun 11: Candidate build repackage with WTP RC4 and vote for the candidate build. <br/>
 +
 +
 +
 +
'''Post BIRT BIRT 2.2 RC4 through Ganymede Release'''
 +
 +
Thursday June 10 until Friday June 17 (Ganymede Release): Testing Pass
 +
 +
Additional RC Builds will be scheduled as necessary

Revision as of 01:25, 8 May 2008

Purpose

This document describes a set of ramp down rules for the BIRT 2.3 Release. The Builds and Release decisions occurs on the dates listed for each Release Candidate

Date

May 6 : BIRT 2.3 RCO

Through May 4, Testing and Fix pass.
Monday May 5 : BIRT 2.3 RCO Candidate build
Monday May 5 until Tuesday May 6: RCO Candidate testing. Ganymede update site update.
Tuesday May 6 until Wednesday May 7: Candidate build repackage with WTP RC0 and vote for the candidate build.


May 20 : BIRT 2.3 RC1

Through May 18, Testing and Fix pass.
Monday May 19 : BIRT 2.3 RC1 Candidate build
Monday May 19 until Tuesday May 20: RC1 Candidate testing. Ganymede update site update.
Tuesday May 20 until Wednesday May 21: Candidate build repackage with WTP RC1 and vote for the candidate build.


May 27 : BIRT 2.3 RC2

Tuesday May 20 through May 25, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday May 26 : BIRT 2.3 RC1 Candidate build
Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update.
Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC2 and vote for the candidate build.


June 3 : BIRT 2.3 RC3

Tuesday May 27 through June 1, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday Jun 2: BIRT 2.3 RC3 Candidate build
Monday Jun 2 until Tuesday June 3: RC3 Candidate testing. Ganymede update site update.
Tuesday Jun 3 until Wednesday Jun 4: Candidate build repackage with WTP RC3 and vote for the candidate build.


June 10: BIRT 2.3 RC4

Thursday June 3 through Tuesday June 8 Testing and Fix pass. All Bug fixes must be approved by the at least two project leads and BIRT PMC
Wednesday June 9: BIRT 2.3 RC4 Candidate build
Wednesday June 9 until Thursday June 10: RC4 Candidate testing. Ganymede update site update.
Tuesday Jun 10 until Wednesday Jun 11: Candidate build repackage with WTP RC4 and vote for the candidate build.


Post BIRT BIRT 2.2 RC4 through Ganymede Release

Thursday June 10 until Friday June 17 (Ganymede Release): Testing Pass

Additional RC Builds will be scheduled as necessary