MemoryAnalyzer/Ramp Down Plan
Ramp down plan
Typically the last week of a Milestone is for testing, and fixing only regressions and P1 or blocking defects. For milestones, the component lead (or delegate) is enough to review and approve a bug.
For M7, we plan to be API and feature complete, so there will be no breaking API changes and no new feature requests will be accepted.
For RC1 - RC2 only bugfixes to Memory Analyzer functionaliry should be done. The following describes the types of bugs that would be appropriate:
- A regression
- A P1 or P2 bug, one that is blocking or critical
- Minor documentation changes
RC3 - RC4 only bugfixes damaging the build/functionality of the simultaneous release should are allowed