COSMOS v1.1 iteration 2 plan
Schedule for Iteration 2
Design doc every enhancement
- if the enhancement is really small, put in at least a paragraph and a link to the use case for QA and documentation.
- if the enhancement is not small, the design doc needs to explain the change, anyone other than the assignee who is affected, how much work it is, any ramifications, and in general please avoid any changes to 3rd party materials other than removing a dependency on it. We have no guarantee that the change will be approved for COSMOS v1.1.
Bugzillas for this iteration (Jimmy, David, Jason, Saurabh, QA, Doc, Ruth)
Sizing legend:
- Low - takes 1-3 days
- Medium - takes a week
- High - takes more than a week
Status to be filled in by:
- Data Collection bugzilla status (Jimmy Mohsin)
- Data Visualization bugzilla status (Jimmy Mohsin)
- Resource Modeling bugzilla status (David Whiteman)
- Management Enablement bugzilla status (Jason Losh)
- RE/Build bugzilla status (Saurabh Dravid)
- QA bugzilla status (No owner)
- Doc bugzilla status (No owner)
- Legal & release review prep and status (Ruth Lee)
The Status column can have one of these values:
- COMPLETE
- On track
- At risk
- Not containable
- Defer (no longer a priority for this iteration)
- Not started
Priority | Status | Project or subteam | Enhancement | Severity | Description | Blocked by (if applicable) | Owner | Sizing | Design Doc | Use Case |
---|---|---|---|---|---|---|---|---|---|---|
Medium | On track | All | 259001 | Defect | Update the IP log and about.html in v1.1 iteration 2 | Ruth Lee | N/A | N/A | N/A | |