                  This documents related to 2019-12, the Eclipse Foundation's multi-project Simultaneous Release of December 2019.
| Simultaneous Release | ||
| Preceded by SimRel-2019-09 | 2019-12 2019 | Succeeded by SimRel-2020-03 | 
Common information
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release schedule
| Release | Date | Span | Due dates | Notes | 
|---|---|---|---|---|
| 2019-12 M1 | Friday, October 18, 2019 | 10/11 to 10/18 | 
 | 3 weeks from 2019-09 GA | 
| 2019-12 M2 | Friday, November 8, 2019 | 11/01 to 11/08 | 3 weeks from M1 | |
| 2019-12 M3 | Friday, November 29, 2019 | 11/22 to 11/29 | 
 | 3 weeks from M2 | 
| 2019-12 RC1 | Friday, December 6, 2019 | 11/29 to 12/06 | 
 | 1 week from M3 | 
| 2019-12 RC2 | Friday, December 13, 2019 | 12/06 to 12/13 | 1 week from RC1 | |
| Quiet period | 12/13 to 12/17 | No builds during "quiet period". It is assumed all code is done by the end of RC2. | ||
| 2019-12 GA | Wednesday, December 18, 2019 | 
 | 5 days from RC2 | |